Or. Admin. Code § 141-093-0187 - Jackson County Vernal Pools - Review Process for Authorizing Projects
The Department shall review applications for this GP according to OAR 141-093-0100 through 141-093-0135, with the following exceptions:
(1) Initial Review. The Department will
review the application within 30 calendar days of agency receipt of the
application to determine whether the application is complete and the project is
eligible for this GP.
(2)
Departmental Final Review. The Department will render a decision within 60
calendar days of receipt of a complete application.
Notes
Statutory/Other Authority: ORS 196.600 - 196.692 & 196.795 - 196.990
Statutes/Other Implemented: ORS 196.600 - 196.692 & 196.795 - 196.990