Or. Admin. Code § 141-093-0275 - Maintenance Dredging - Specific Conditions
(1) General Conditions Apply. All
requirements, procedures and conditions set forth in OAR 141-093-0135 (General
Conditions) apply to this General Permit, except as follows:
(a) General Condition (8) Pre-construction
Resource Area Fencing or Flagging does not apply; and
(b) General Condition (9) Erosion Control
Methods applies only to maintenance dredging activity involving upland
placement of material.
(2) Removal-General.
(a) To the extent practicable, maintenance
dredging activity must be staged from an upland or vessel-mounted position. If
necessary to achieve the removal, heavy equipment may be staged on or traverse
impervious surfaces in the dry below ordinary high water or highest measured
tide. In such case, equipment must use water quality best management practices
specified in the DEQ-issued Section 401 Water Quality Certification for the
project.
(b) For vessel-mounted
operations, vessels must not be grounded on the bed or banks at any
time.
(c) Accumulated woody debris
within the maintenance dredging footprint may be removed to the extent
necessary to achieve the target bathymetry.
(3) Removal by Hydraulic Pipeline Dredge.
(a) To the extent practicable and as material
characteristics allow, the working end of the dredge ladder must be kept buried
at a target depth of at least 24 inches below the bottom of the waterway. The
intake may be raised no more than 3 feet above the bed for the minimum time
necessary for purging or flushing. No back-flushing of the pipeline is allowed.
No jetting of sediment is allowed unless approved by the Department pursuant to
OAR 141-093-0260(3).
(b)The
pipeline and any anchors or floats must be removed from the waterway
immediately upon completion of the maintenance dredging activity unless another
minimum necessary timeframe is approved by the Department. In no case will the
pipeline, anchors, floats or other equipment be permanently placed in waters of
this State.
(c) Pressure in the
dredge pipeline must be continuously monitored during operation. In the event
of a sudden and sustained pressure drop, dredging activity shall immediately
stop. Any breach of the pipeline must be repaired prior to restarting dredging
operation.
(4) Removal
by Closed Bucket. To the extent material characteristics allow, the bucket must
be sealed in the closed position to minimize sediment re-suspension. Moving
material on the bottom to consolidate it before lifting is
prohibited.
(5) Material Transport.
For dredged material transported by vessel or other over-water conveyance:
(a) All dredged materials must be placed in
vessels or other conveyances equipped such that no dredged material discharges
to waters of this State during loading, transfer and unloading activity for
upland placement.
(b) Vessels must
be staged such that there is no grounding on the bed or banks at any
time.
(6) Placement -
General. Unless otherwise authorized by the governing regulatory agency or
agencies, removed material must not be placed in any wetland, Federal Emergency
Management Administration designated floodway, or in an area historically
subject to landslides.
(7) Upland
Placement.
(a) Removed material placed in an
upland site must meet the Oregon Department of Environmental Quality definition
of clean fill or the use must be specifically allowed by the Oregon Department
of Environmental Quality by rule, permit, or other authorization.
(b) Waste waters from the upland placement
site must have adequate settling time before being discharged into a water of
this State. Water discharged from the upland placement site must meet water
quality requirements of the Oregon Department of Environmental
Quality.
(8) Flowlane
Placement. Flowlane placement must occur on the ebb tide only and only when
there is sufficient current to disperse the material to prevent
shoaling.
(9) Ocean Placement.
Ocean placement may only occur as authorized by a USEPA letter of
concurrence.
(10) Ocean Shore
Permit. If the project includes direct placement of material on the ocean
shore, a separate Ocean Shore Permit, administered by Oregon Parks and
Recreation Department, will be required to authorize that activity.
(11) State-Owned Waterways. Maintenance
dredging in a state-owned waterway may be subject to a Short-Term Access
Agreement with the Department. The placement of state-owned material on uplands
is subject to a Sand and Gravel Lease or License from the Department. Any
beneficial use of state-owned material may be subject to royalty payments to
the Department.
(12) Fish
Entrainment. The authorization holder must immediately report any fish observed
that are entrained by operations to the nearest OR Department of Fish and
Wildlife office. The permittee must provide access for OR Department of Fish
and Wildlife staff to enter the project site for making fish entrainment
observations.
(13) Post-Activity
Reporting. Within 90 days of maintenance dredging completion, the authorization
holder must submit to the Department a scaled drawing illustrating the actual
removal area and post-removal depths achieved using the same datum as used in
the application.
(14) Modifying
Conditions. The Department may modify the conditions of the authorization at
any time if necessary to reduce or eliminate adverse effects to water
resources.
Notes
Statutory/Other Authority: ORS 196.817
Statutes/Other Implemented: ORS 196.600-196.990
State regulations are updated quarterly; we currently have two versions available. Below is a comparison between our most recent version and the prior quarterly release. More comparison features will be added as we have more versions to compare.
No prior version found.