Or. Admin. Code § 330-220-0090 - Amendments to Preliminary Certifications
(1) Amendments are documentation of changes
to the project described in the application for preliminary certification .
(2) An applicant must submit
requests for amendments prior to issuance of the final certification .
(3) Failure of an applicant to
submit documentation to the department of changes to the project may result in
denial of final tax credit certification.
(4) Changes to the project must be documented
by the applicant . The applicant must submit an amendment request on the form
specified in the Opportunity Announcement along with the required amendment
fee, except that:
(a) Equipment substitutions
that do not reduce the project 's capabilities, do not reduce the project 's
capacity and are within five percent of the stated fuel displacement may be
documented in the project 's status report, the final certification application
form, an amendment request form or by notifying the department in writing.
These changes do not require an amendment fee. The department may require the
applicant to demonstrate that the change does not reduce the project 's
capabilities, does not reduce the project 's capacity and is within five percent
of the stated fuel displacement.
(b) A change of responsible party information
may be documented by notifying the department in writing. These changes do not
require an amendment fee.
(5) Undeclared changes found in the
application for final certification or through later inspection must be
documented by the applicant by submitting an amendment request on the form
specified in the Opportunity Announcement with the required amendment fee.
Undeclared changes that result in no reduction to the project 's capabilities,
no reduction to the project 's capacity and are within five percent of the
stated fuel displacement may be documented by the department through an
inspection report or final review and do not require an amendment fee.
(6) When documenting a change, the
applicant must demonstrate that the alternative fuel vehicle project , with the
proposed change, will continue to meet the requirements of statute, rule and
the Opportunity Announcement; be technically feasible; will operate as
represented and would remain in operation for at least five years. The
applicant has the responsibility to provide an amendment request with complete
technical documentation supporting the proposed amendment. The department may
deny amendments submitted without such justification.
(7) An amendment may result in a reduction in
tax credit, but may not increase the tax credit amount certified in the
preliminary certificate.
(8) If an
amendment request does not include all information needed to complete the
review, the department may provide the applicant a written request for
additional information. If the applicant does not provide the requested
information to the department within 30 calendar days of the date of the
department 's written request, the department may deny the amendment request to
amend the preliminary certification .
(9) Requests for amendments must include
payment of the appropriate fee, unless provided otherwise in this rule.
(10) The department will decide
whether to approve the request.
(a) If the
amendment request is approved prior to submission the application for final
certification , the department will draft an amended preliminary certification ,
which may contain new or amended conditions and requirements.
(b) If the amendment request is approved
after submission of application for final certification , the department will
notify the applicant in writing. The amendment may result in a reduction in tax
credit and inclusion of conditions in the final certificate.
(c) If the amendment request is denied, the
department will notify the applicant in writing. The notice will include the
reasons for the denial of the amendment request. The amendment fee will not be
applied to future amendments.
(d)
No later than 60 days after the department denies an amendment request or
reduces the tax credit under this section, the applicant may request
reconsideration in writing. The request for reconsideration will not extend
other mandated timelines, such as the expiration date of the preliminary
certificate.
Notes
Stat. Auth.: ORS 469.040, 469B.326, 469B.332, 469B.347
Stats. Implemented: ORS 315.336 & 469B.320 - 469B.347