Or. Admin. Code § 340-039-0025 - Requirements of a Water Quality Trading Plan
(1) An eligible entity may not engage in
water quality trading unless DEQ has reviewed and approved that entity's water
quality trading plan. The use of credits will be authorized after all elements
of a DEQ-approved trading plan required by subsection (5) of this rule are
incorporated as enforceable conditions of an NPDES permit issued under OAR
chapter 340 division 045 or a 401 water quality certification issued under OAR
chapter 340 division 048.
(2) For
NPDES permittees trading may be proposed as part of a permittee's application
for permit renewal or modification.
(3) DEQ must provide an opportunity for
public notice and comment on a trading plan before approving the trading plan.
DEQ may amend the trading plan or require amendments to the trading plan prior
to approval. Individual trading projects must be consistent with an approved
trading plan. Individual trading projects do not require separate public notice
and comment.
(4) A trading plan
must be consistent with an applicable DEQ-issued trading framework if such a
framework exists at the time DEQ approves the trading plan.
(5) A trading plan must include all of the
following elements and a description of how the elements were derived or
calculated:
(a) The parameter for which water
quality trading is proposed;
(b)
Trading baseline: A trading plan must identify any applicable regulatory
requirements from OAR
340-039-0030(1)
that apply within the trading area and that must be implemented to achieve
baseline requirements;
(c) Trading
area: A description of the trading area including identification of the
location of the discharge to be offset, its downstream point of impact, if
applicable, where trading projects are expected to be implemented, and the
relationship of the trading projects to beneficial uses in the trading area;
(d) BMPs: A description of the
water quality benefits that will be generated, the BMPs that will be used to
generate water quality benefits, and applicable BMP quality standards;
(e) Trading ratios: A description
of applicable trading ratios, the basis for each applicable trading ratio,
including underlying assumptions for the ratio, and a statement indicating
whether those ratios increase or decrease the size of a credit obligation or
the number of credits generated from an individual trading project;
(f) Credits: A description of the credits
needed to meet water quality-based requirements of an NPDES permit or 401 water
quality certification, including:
(A)
Quantity and timing: The number of credits needed and any credit generation
milestones, including a schedule for credit generation;
(B) Methods used: How credits will be
quantified, including the assumptions and inputs used to derive the number of
credits; and
(C) Duration of
credits: A description of the length of time credits are expected to be used.
(g) Monitoring. The
trading plan must include a description of the following:
(A) Proposed methods and frequency of trading
project BMP monitoring; and
(B)
Proposed methods and frequency of how water quality benefits generated by a
trading project will be monitored;
(h) Trading Plan Performance Verification: A
description of how the entity will verify and document for each trading project
that BMPs are conforming to applicable quality standards and credits are
generated as planned; and
(i)
Tracking and Reporting: A description of how credit generation, acquisition and
usage will be tracked and how this information will be made available to the
public.
(6) Adaptive
Management: Trading plans must include a description of how monitoring and
other information may be used over time to adjust trading projects and under
what circumstances;
(7) Trading
Plan Revision: An approved trading plan must be revised during permit or 401
water quality certification renewal or if there is a change in circumstances
that affects a trading plan element required by subsection (5) of this rule.
Revised trading plans must be submitted to DEQ for review and approval and must
be given an opportunity for public notice and comment. DEQ will reopen and
modify the permit or 401 water quality certification for any revisions
affecting an enforceable condition.
Notes
Stat. Auth.: ORS 468.020, 468B.020, 468B.030, 468B.035, 468B.555
Stats. Implemented: ORS 468B.555
State regulations are updated quarterly; we currently have two versions available. Below is a comparison between our most recent version and the prior quarterly release. More comparison features will be added as we have more versions to compare.
No prior version found.