Or. Admin. Code § 340-040-0190 - Update Procedure
(1) A Wellhead
Protection Plan must be recertified every five years from the date of prior
Department certification.
(2)
Recertification of the present Plan can take place if all the following
conditions apply:
(a) No conditions that could
potentially modify the boundaries of the Wellhead Protection Area have
occurred;
(b) An updated inventory
is completed and submitted which shows that no new potential sources of
contamination have moved into the Wellhead Protection Area which are not
addressed in the existing Plan;
(c)
The management practices outlined in the existing Plan are still appropriate
and being implemented;
(d) The
existing contingency element in the Plan is still relevant; and
(e) All signatories to the existing Plan
agree to recertify the Plan by signing the recertification request
letter.
(3) If a
certified Plan cannot meet the conditions under section (2) of this rule, then
a revised Wellhead Protection Plan must be resubmitted for certification. A
revised plan shall require:
(a) Form a Team
to develop the Plan. The Team can either be a new group formed for the specific
purpose of developing a Plan or it can be an existing group that is assigned
the additional duty of developing a Plan;
(b) Identify the elements under OAR
340-040-0170 where the Plan is
no longer adequate or relevant;
(c)
Modify the Plan in those areas identified in subsection (b) of this section to
meet conditions outlined in OAR
340-040-0170 and OAR
340-040-0180;
(d) Perform and submit a new potential source
inventory; and
(e) Submit to the
Department for review and certification per OAR
340-040-0180.