Or. Admin. Code § 340-045-0030 - Application for NPDES or WPCF Permit
(1) Any person wishing to obtain a new or
renewal NPDES or WPCF permit from DEQ must submit a written application at
least 180 days before an NPDES permit is needed or at least 60 days before a
WPCF permit is needed on a form DEQ provides. The Director may grant permission
in writing for a later date to submit a new or renewal application. The
Director will not grant permission for a renewal application to be submitted
later than the existing permit's expiration date.
(2) Any person wishing to modify their NPDES
or WPCF permit must submit a written application on a form DEQ provides.
Applications must be submitted well in advance of the needed modification in
order to process the request as OAR
340-045-0055 requires.
(3) All application forms must be completed
in full and signed by the applicant or the applicant's legally authorized
representative. The name of the applicant must be the legal name of the owner
of the facility or the owner's agent or the lessee responsible for operating
and maintaining the facility. DEQ will consider applications that are correctly
signed and appear administratively complete timely upon receipt. A request for
further information under section (5) of this rule will not affect an
application's timeliness.
(4) DEQ
will not accept for filing applications that are obviously incomplete,
unsigned, improperly signed, or that do not contain the required exhibits
clearly identified. DEQ will return these applications to the applicant for
completion.
(5) Within 45 days
after receiving an application, DEQ will preliminarily review an application to
determine the adequacy of the information submitted. Failure to complete this
review within 45 days does not preclude DEQ from later requesting further
information from the applicant as provided in this section.
(a) If DEQ determines that additional
information is needed, it will promptly request in writing the needed
information from the applicant. The application will be considered withdrawn if
the applicant fails to submit the requested information within 90 days of the
request or such other time as DEQ establishes in writing.
(b) If DEQ determines that additional
measures are necessary to gather facts regarding the application, it will
notify the applicant in writing that such measures will be instituted and
provide the timetable and procedures to be followed. The application will be
considered withdrawn if the applicant fails to comply with the additional
measures.
(6) If upon
review of an application, DEQ determines that a permit is not required, DEQ
will notify the applicant in writing of this determination. Such notification
constitutes final action by DEQ on the application.
(7) DEQ will accept as an application filed
under this section an application that has been filed with the U.S. Army Corps
of Engineers in accordance with Section 13 of the Federal Refuse Act, or an
NPDES application that has been filed with the U.S. Environmental Protection
Agency provided the application is complete and the information on the
application is still current.
Notes
Statutory/Other Authority: ORS 468.020, 468B.020 & 468B.035
Statutes/Other Implemented: ORS 468.065, 468B.015, 468B.035 & 468B.050