Or. Admin. Code § 340-052-0040 - Responsibility of Treatment Works Owners, Designs Engineers and Developers After Approval of Plans for (Domestic) Sewage Projects
(1) Construction of all projects must be in
accordance with the project plans and specifications approved by the
Department. No substantial change in or deviation from such plans and
specifications shall be made without the prior written approval of the
Department, which shall make the final determination whether or not a change or
deviation is in fact substantial.
(2) The owner of the sewerage system
(generally a municipality) as recipient of any construction work on its system
has a vested responsibility to review and approve project plans prior to the
start of construction. Department approval of plans under these rules does not
preclude the right and responsibility of review and approval by the owner. The
owner may adopt more stringent construction standards and impose special
conditions for sewer use, service connection, and related activities.
Department approval of plans in such cases is contingent upon similar approval
by the owner. Submittal of plans to the Department through the owner and prior
approval of plans by the owner is encouraged.
(3) Inspection and certification of proper
construction shall be governed by the following provisions:
(a) The construction of all sewerage projects
shall be under the supervision of and shall be thoroughly inspected by the
design engineer or his authorized representative, unless relieved under
subsection (b) of this section. At the completion of the project, he shall
certify in writing to the owner and the Department that such construction was
inspected by him and found to be in accordance with the plans and
specifications, including any changes therein approved by the Department.
Nothing in the foregoing exempts an owner from monitoring the project for
conformance to require-ments and performing supplementary inspections or
prevents an owner's qualified staff from assuming responsibility for inspection
and certification;
(b) If the
design engineer is to have no further involvement or have limited involvement
with the project after obtaining Department approval of plans, he must so
notify the Department, the owner, and the developer upon submittal of plans or
immediately upon being disassociated or limited in control over materials or
workmanship within the project. (Nothing precludes either the owner or the
developer from giving such notice if this is more appropriate). Thereupon, if
the project is to continue on to construction, the owner shall assume necessary
responsibility for satisfactory construction of the project in accordance with
the approved plans. He shall employ or apply such construction
engineering/inspection services as appropriate for the project. The owner shall
thereupon certify in accordance with subsection (a) of this section. No project
shall proceed to construction without adequate and capable construction
engineering/inspection services. (This assumption of construction
engineering/inspection services responsibility by the owner does not
necessarily relieve the design engineer of design responsibility);
(c) Sewerage system integrity and
watertightness is the system owner's ultimate responsibility. He shall monitor
all private sewer construction and control all common sewer construction in the
sewerage system to the extent necessary to this end.
(4) An appropriate final operation and
maintenance manual, approved by the Department shall be prepared and submitted
to the owner by the design engineer for all treatment works, disposal systems,
and list stations prior to start up of such facilities.
Notes
Stat. Auth.: ORS 454.626, ORS 454.780 & ORS 468.020
Stats. Implemented: ORS 468B.055
State regulations are updated quarterly; we currently have two versions available. Below is a comparison between our most recent version and the prior quarterly release. More comparison features will be added as we have more versions to compare.
No prior version found.