Or. Admin. Code § 340-071-0175 - Certificate of Satisfactory Completion
(1) The agent may issue a Certificate of
Satisfactory Completion for a system installation if, the agent inspects and
system and determines the system complies with applicable requirements in this
division and OAR chapter 340, division 073 and the permit's
conditions.
(2) If an agent
determines an installation does not comply with the requirements in section (1)
of this rule, the agent must notify the permittee in writing or post a
Correction Notice on the site. The notice must explain the system deficiencies
and corrective action required.
(3)
If an agent does not inspect a system within 7 days after notification of
completion or waives the inspection under OAR
340-071-0170(2)
or 340-071-0400(6)(d),
a Certificate of Satisfactory Completion will be deemed to have been issued by
operation of law. In such cases, a modified Certificate will be issued to the
owner.
(4) A system may be
backfilled (covered) after installation only after:
(a) The agent has notified the permittee that
the inspection will not be conducted;
(b) The agent has inspected the system and
issued a Certificate of Satisfactory Completion; or
(c) A Certificate of Satisfactory Completion
has been issued by operation of law under section (3) of this rule.
(5) The permittee must ensure
satisfactory completion of a system installation within 30 days after written
notification or posting of a Correction Notice under section (2) of this rule
unless the agent agrees to a later time.
(6) A person may not connect to or use any
system completed after January 1, 1974, unless a Certificate of Satisfactory
Completion has been issued for the installation or deemed issued by operation
of law under this rule.
(7) Unless
the agent requires otherwise, the system installer must backfill (cover) a
system within 10 days after issuance of a Certificate of Satisfactory
Completion for that system.
(8) A
Certificate of Satisfactory Completion is valid for a period of five years for
connection of the system to the facility for which it was constructed. After
the five-year period, an Authorization Notice, alteration permit, or
construction-installation permit may be required under OAR
340-071-0160,
340-071-0205, or
340-071-0210.
(9) A permittee may appeal the denial or
revocation of a Certificate of Satisfactory Completion under ORS
183.310 through
183.550 and OAR chapter 340,
division 11.
Notes
Statutory/Other Authority: ORS 454.625 & 468.020
Statutes/Other Implemented: ORS 454.655
State regulations are updated quarterly; we currently have two versions available. Below is a comparison between our most recent version and the prior quarterly release. More comparison features will be added as we have more versions to compare.
No prior version found.