Or. Admin. Code § 340-083-0100 - Grant Agreements and Conditions

(1) Following approval and selection of the application, DEQ and the applicant shall enter into an agreement. The agreement must include but is not limited to the following:
(a) Statement of work and schedule;
(b) Requirements of progress reports;
(c) Project management requirements as DEQ specifies;
(d) Statement of authorized activities for rolling stock, purchased in whole or in part with grant funding, during its expected service life;
(e) End date - term of project and grant;
(f) Method of payment;
(g) Terms and conditions of the grant;
(h) Requirements for sharing of information resulting from project; and
(i) Requirements of a project completion report.
(2) DEQ may allow an extension of time for a grantee to complete a project, upon written request by the grantee made prior to the agreement expiration date and receipt of acceptable documentation of need.
(3) DEQ may at any time review and audit requests for payment and make adjustments for, but not limited to, math errors, items not built or bought, unacceptable constructions or lack of progress under the grant.

Notes

Or. Admin. Code § 340-083-0100
DEQ 6-1991, f. & cert. ef. 5-2-91; DEQ 7-2000, f. & cert. ef. 6-2-00; DEQ 2-2016, f. & cert. ef. 2/4/2016

Stat. Auth.: ORS 45A.025 & 468.020

Stats. Implemented: ORS 459A.120