Or. Admin. Code § 340-093-0250 - Landfill Siting: Request for DEQ Assistance
(1) A city or county responsible for
implementing a Department approved Solid Waste Management Plan which identifies
the need for a landfill may request assistance from the Department in
establishing a landfill under ORS
459.047.
(2) Applications for requests for assistance
in siting landfills under ORS
459.047 shall be in the form of
a letter signed by the governing body of the city or county with attachments as
necessary to fully describe the need and justification for the request, need
for the site as outlined in the Department approved Solid Waste Management Plan
and types of assistance required.
(3) When the request for assistance includes
Department siting of the landfill under ORS
459.047, exhibits and
information shall be submitted which document the following:
(a) The local government has an adopted,
Department approved Solid Waste Management Plan which identifies the need for a
landfill;
(b) The local government
has reevaluated the plan in consultation with the Department and has confirmed
that siting a landfill in the immediate future is still needed;
(c) An explanation of why the local
government is unable to proceed successfully to site the landfill, including a
discussion of progress to date and the obstacles to be overcome;
(d) All pertinent reports, plans, documents
and records relative to the siting process to date will be made available to
the Department at the Department's request;
(e) The local government has carried out a
process for landfill siting (with technical assistance from the Department if
requested) including a minimum of the following:
(A) Alternative sites have been reviewed and
ranked as to adequacy and probable acceptability based upon locally developed
criteria and applicable laws and regulations;
(B) Information has been gathered on at least
the top ranked site sufficient to satisfy the requirements of the "site
characterization report(s)" provided for in OAR
340-093-0130. Certain
requirements of the "site characterization report(s)" may be waived, for the
purpose of this section, by the Department upon a demonstration of prohibitive
cost or legal constraint;
(C) A
public participation process, including the use of a citizens advisory
committee or other approach which provides for public access, review and input
has been carried out in the siting process.
(4) The Department shall give reasonable
public notice of each such request, including the prompt publication of a
summary of such request in the Secretary of State's Bulletin.
(5) Requests for siting under ORS 459.047will
be reviewed by the Commission and written findings as to the acceptability of
the process under subsection (3)(e) of this rule will be prepared. Should the
process be found incomplete, the Commission may request the Department or the
local government to complete the process.
(6) Landfill siting in Marion, Polk,
Clackamas, Washington or Multnomah Counties under ORS
459.049:
(a) Public comment to determine need. Prior
to the Commission making a determination of need for any landfill site under
ORS 459.049, the Department shall
give prior reasonable public notice of, and hold a public informational hearing
on, the need for the landfill site;
(b) Public hearing in area affected by
proposed site. Prior to siting a landfill under ORS
459.049, the Department shall
give prior reasonable public notice of and hold a public informational hearing
in the area affected by the proposed site.
Notes
Stat. Auth.: ORS 459
Stats. Implemented: ORS 459.017, ORS 459.035 & ORS 459.047
State regulations are updated quarterly; we currently have two versions available. Below is a comparison between our most recent version and the prior quarterly release. More comparison features will be added as we have more versions to compare.
No prior version found.