If a municipal solid waste landfill is subject to 40 CFR,
Part 258 as provided in
40 CFR, §
258.1
, the owner or operator shall
comply with closure and post-closure care requirements in 40 CFR, Part
258, Subpart F. All municipal solid waste permittees shall also comply
with this rule for any landfill that closes after January 1, 1980.
(1) When solid waste is no longer received at
a municipal solid waste landfill, the person who holds or last held the permit
issued underORS 459.205 or, if the person who
holds or last held the permit fails to comply with this section, the person
owning or controlling the property on which the landfill is located, shall
close and maintain the site according to the requirements of ORS Chapter 459,
all applicable rules adopted by the Commission underORS
459.045 and all requirements
imposed by the Department as a condition to renewing or issuing a disposal site
permit.
(2) Unless otherwise
approved or required in writing by the Department, no person shall permanently
close or abandon a municipal solid waste landfill, except in the following
manner:
(a) All areas containing solid waste
not already closed in a manner approved by the Department shall be covered with
at least three feet of compacted soil of a type approved by the Department
graded to a minimum two percent and maximum 30 percent slope unless the
Department authorizes a lesser depth or an alternative final cover design. In
applying this standard, the Department will consider the potential for adverse
impact from the disposal site on public health, safety or the environment, and
the ability for the permittee to generate the funds necessary to comply with
this standard before the disposal site closes. A permittee may request that the
Department approve a lesser depth of cover material or an alternative final
cover design based on the type of waste, climate, geological setting, degree of
environmental impact;
(b) Final
cover material shall be applied to each portion of a municipal solid waste
landfill within 60 days after said portion reaches approved maximum fill
elevation, except in the event of inclement weather, in which case final cover
shall be applied as soon as practicable;
(c) The finished surface of the closed areas
shall consist of soils of a type or types consistent with the planned future
use and approved by the Department. Unless otherwise approved by the
Department, a vegetative cover of native grasses shall be promptly established
over the finished surface of the closed site;
(d) All surface water must be diverted around
the area of the disposal site used for waste disposal or in some other way
prevented from contacting the waste material;
(e) All systems required by the Department to
control or contain discharges to the environment must be completed and
operational.
(3) Closure
of municipal solid waste landfills shall be in accordance with the detailed
Final Engineered Site Closure Plans approved in writing by the Department
pursuant to OAR
340-094-0110.
(4) Closure approval:
(a) When closure is completed, the permittee
shall submit a written request to the Department for approval of the
closure;
(b) Within 30 days of
receipt of a written request for closure approval, the Department shall inspect
the facility to verify that closure has been effected in accordance with the
approved closure plan and the provisions of OAR Chapter 340, Divisions 93 and
94;
(c) If the Department
determines that closure has been properly completed, the Department shall
approve the closure in writing. Closure shall not be considered complete until
such approval has been made. The date of approval notice shall be the date of
commencement of the post-closure period.
Notes
Or. Admin. Code
§
340-094-0120
DEQ 2-1984, f. & ef.
1-16-84; DEQ 5-1993, f. & cert. ef. 3-10-93, Renumbered from 340-061-0042;
DEQ 10-1994, f. & cert. ef. 5-4-94; DEQ 2-1995, f. & cert. ef.
1-10-95
Stat. Auth.: ORS
459.045,ORS
459.209,ORS
459.248,ORS
459.270,ORS
459.272 & ORS
468.020
Stats. Implemented:ORS
459.268