Or. Admin. Code § 340-095-0060 - Closure and Post-Closure Care: Closure Plans
To comply with the financial assurance requirements of OAR 340-095-0090(1) (a):
(1) Two types of written closure plans shall
be prepared:
(a) The two types of closure
plan are:
(A) A conceptual "worst-case"
closure plan, for closing the site at its maximum capacity. The plan shall
contain sufficient detail to allow a reasonable estimate of the cost of closing
the non-municipal land disposal site as required by OAR
340-095-0090(1)(a);
and subsequently
(B) A Final
Engineered Site Closure Plan, as required by OAR
340-095-0050(2)(a),
which shall replace the conceptual "worst-case" closure plan.
(b) Schedule for preparation of
closure plans:
(A) The conceptual
"worst-case" closure plan shall be prepared and placed in the facility
operations office or other location approved by the Department, and the
Director shall be notified of that action no later than April 9, 1995 or by the
initial receipt of waste, whichever is later;
(B) The Final Engineered Site Closure Plan
shall be prepared and submitted to the Department five years before the
anticipated final closure date, or at a date specified in the permittee's
closure permit pursuant to OAR
340-095-0050(2)(a).
(2) Requirements for
closure plans. A closure plan shall specify the procedures necessary to
completely close the non-municipal land disposal site at the end of its
intended operating life:
(a) Requirements for
the conceptual "worst-case" closure plan shall consist of at least the
following:
(A) A description of the steps
necessary to close all non-municipal land disposal units at any point during
their active life;
(B) A
description of the final cover system that is designed to minimize infiltration
and erosion;
(C) An estimate of the
largest area of the non-municipal land disposal unit ever requiring a final
cover; and
(D) An estimate of the
maximum inventory of wastes ever on-site over the active life of the
facility.
(b)
Requirements for the Final Engineered Site Closure Plan. In addition to the
requirements for the conceptual "worst-case" closure plan, the Final Engineered
Site Closure Plan shall consist of at least the following elements:
(A) Detailed plans and specifications
consistent with the applicable requirements of OAR
340-093-0140 and
340-095-0030(2),
unless an exemption is granted as provided in OAR
340-093-0070(5);
NOTE:If some of this information has been previously submitted, the permittee shall review and update it to reflect current conditions and any proposed changes in closure activities.
(B) A description of how and when
the non-municipal land disposal site will be closed. If a landfill, the
description shall, to the extent practicable, show how the landfill will be
closed as filling progresses to minimize the area remaining to be closed at the
time that the site stops receiving waste. A time schedule for completion of
closure shall be included;
(C)
Details of final closure. If a landfill, details of final cover including soil
texture, depth and slope;
(D)
Details of surface water drainage diversion; and
(E) Other information requested by the
Department necessary to determine whether the non-municipal land disposal site
will comply with all applicable rules of the Department.
(3) Department approval. The Final
Engineered Site Closure Plan is subject to written approval by the Department.
After approval by the Department, the permittee shall implement the Final
Engineered Site Closure Plan within the approved time schedule.
(4) Amendment of Plan. The approved Final
Engineered Site Closure Plan may be amended at any time as follows:
(a) The permittee must amend the plan
whenever changes in operating plans or facility design, or changes in OAR
Chapter 340 Divisions 93 through 97, or events which occur during the active
life of the landfill significantly affect the plan. The permittee must also
amend the plan whenever there is a change in the expected year of closure. The
permittee must submit the necessary plan amendments to the Department for
approval within 60 days after such changes or as otherwise required by the
Department;
(b) The permittee may
request to amend the plan to alter the closure requirements based on cause. The
request must include evidence demonstrating to the satisfaction of the
Department that:
(A) The nature of the
non-municipal land disposal site makes the closure requirements unnecessary;
or
(B) The requested alteration of
closure requirements is necessary to prevent threat of adverse impact on public
health, safety or the environment.
(c) The Department may amend a permit to
require the permittee to modify the plan if it is necessary to prevent the
threat of adverse impact on public health, safety or the environment. Also, the
Department may alter the closure requirements based on cause.
Notes
Stat. Auth.:ORS 459.045,ORS 459A.025 &ORS 468.020
Stats. Implemented:ORS 459.268 &ORS 459.270