Or. Admin. Code § 340-141-0282 - Plan Maintenance and Use
(1)
At least one copy of the plan must be kept in a central location accessible at
any time by the incident commander or spill response manager named in
accordance with OAR 340-141-0265(7).
(2) A High Hazard Rail owner or their
designee must implement the plan in the event of a spill. The owner of the High
Hazard Rail Line must receive approval from DEQ before it conducts any major
aspect of the spill response contrary to the plan unless:
(a) Such actions are necessary to protect
human health and safety;
(b) Such
actions must be performed immediately in response to unforeseen conditions to
avoid additional environmental damage; or
(c) The plan holder has been directed to
perform such actions by the Department or the United States Coast
Guard.
Notes
Statutory/Other Authority: ORS 468B.437
Statutes/Other Implemented: ORS 468B.300 - 468B.500
State regulations are updated quarterly; we currently have two versions available. Below is a comparison between our most recent version and the prior quarterly release. More comparison features will be added as we have more versions to compare.
No prior version found.