Or. Admin. Code § 340-210-0240 - Notice of Construction and Approval of Plans: Construction Approval
(1) Approval to
Construct:
(a) For Type 1 changes, the owner
or operator may proceed with the construction or modification 10 calendar days
after DEQ receives the notice required in OAR
340-210-0230 or on the date that
DEQ approves the proposed construction in writing, whichever is sooner, unless
DEQ notifies the owner or operator in writing that the proposed construction or
modification is not a Type 1 change.
(b) For Type 2 changes, the owner or operator
may proceed with the construction or modification 60 calendar days after DEQ
receives the notice and fees required in OAR
340-210-0230 or on the date that
DEQ approves the proposed construction in writing, whichever is sooner, unless
DEQ notifies the owner or operator in writing that the proposed construction or
modification is not a Type 2 change.
(c) For Type 3 changes, the owner or operator
must obtain either a Construction ACDP or a new or modified Standard ACDP in
accordance with OAR 340 division 216 before proceeding with the construction or
modification.
(d) For Type 4
changes, the owner or operator must obtain a new or modified Standard ACDP
before proceeding with the construction or modification. Type 4 changes may
also be subject to OAR 340 division 224, New Source Review
requirements.
(2)
Approval to construct does not relieve the owner of the obligation of complying
with applicable requirements.
(3)
Notice of Completion. Unless otherwise specified in the construction ACDP or
approval, the owner or operator must notify DEQ in writing that the
construction or modification has been completed using a form furnished by DEQ.
Unless otherwise specified, the notice is due 30 days after completing the
construction or modification. The notice of completion must include the
following:
(a) The date of completion of
construction or modification; and
(b) The date the stationary source, device,
activity, process, or air pollution control device was or will be put in
operation.
(4) Order
Prohibiting Construction or Modification. If at any time, DEQ determines that
the proposed construction is not in accordance with applicable statutes, rules,
regulations, and orders, DEQ will issue an order prohibiting the construction
or modification. The order prohibiting construction or modification will be
forwarded to the owner or operator by certified mail.
(5) Hearing. A person against whom an order
prohibiting construction or modification is directed may request a contested
case hearing within 20 days from the date of mailing the order. The request
must be in writing, state the grounds for hearing, and be mailed to the
Director of DEQ. The hearing will be conducted pursuant to the applicable
provisions in division 11 of this chapter.
[NOTE: This rule is included in the State of Oregon Clean Air Act Implementation Plan that EQC adopted under OAR 340-200-0040.]
Notes
Statutory/Other Authority: ORS 468.020, 468A.025, 468A.040, 468A.050, 468A.055, 468A.070 & 468A.310
Statutes/Other Implemented: ORS 468A.025, 468A.035, 468A.040, 468A.050, 468A.055, 468A.070 & 468A.310
State regulations are updated quarterly; we currently have two versions available. Below is a comparison between our most recent version and the prior quarterly release. More comparison features will be added as we have more versions to compare.
No prior version found.