Or. Admin. Code § 340-212-0230 - Deadlines for Submittals
(1) Large
regulated pollutant-specific emissions units. For all regulated
pollutant-specific emissions units with the potential to emit the applicable
regulated pollutant in an amount equal to or greater than 100 percent of the
amount, in tons per year, required for a source to be classified as a major
source, the owner or operator must submit the information required under OAR
340-212-0220 at the following
times:
(a) The owner or operator must submit
information as part of an application for an initial Oregon Title V Operating
Permit if, by that date, the application either:
(A) Has not been filed; or
(B) Has not yet been determined to be
complete by DEQ.
(b)
The owner or operator must submit information as part of an application for a
significant permit revision under OAR
340-218-0080, but only with
respect to those regulated pollutant-specific emissions units for which the
proposed permit revision applies;
(c) The owner or operator must submit any
information not submitted under the deadlines set forth in subsections (1)(a)
and (b) as part of the application for the renewal of an Oregon Title V
Operating Permit.
(2)
Other regulated pollutant-specific emissions units. For all other regulated
pollutant-specific emissions units subject to OAR
340-212-0220 through
340-212-0280 and not subject to
section (1), the owner or operator must submit the information required under
340-212-0220 as part of an
application for a renewal of an Oregon Title V Operating Permit.
(3) A permit reopening to require the
submittal of information under this rule is not required by OAR
340-218-0200(1)(a)(A).
If, however, an Oregon Title V Operating Permit is reopened for cause by EPA or
DEQ pursuant to OAR 340-218-0200(1)(a)(C), (D), or
(E), the applicable agency may require the
submittal of information under this rule for those regulated pollutant-specific
emissions units that are subject to OAR
340-212-0200 through
340-212-0280 and that are
affected by the permit reopening.
(4) Until DEQ approves monitoring plans that
satisfy the requirements of OAR
340-212-0200 through
340-212-0280, the owner or
operator is subject to the requirements of OAR
340-218-0050(3)(a)(C).
Notes
Stat. Auth.: ORS 468.020 & 468A.310
Stats. Implemented: ORS 468A.310
State regulations are updated quarterly; we currently have two versions available. Below is a comparison between our most recent version and the prior quarterly release. More comparison features will be added as we have more versions to compare.
No prior version found.