Or. Admin. Code § 340-230-0359 - Compliance Schedule

(1) Compliance with the revised April 28, 2009 emission limits in OAR 340-230-0310 is required as expeditiously as practicable, but not later than April 28, 2009, except as provided in section (2) of the rule.
(2) The owner or operator of an affected facility who is planning an extensive emission control system upgrade may petition the Administrator for a longer compliance schedule and must demonstrate to the satisfaction of the Administrator the need for additional time. If approved, the schedule may exceed the schedule in section (1) of this rule, but cannot exceed May 10, 2011.

Notes

Or. Admin. Code § 340-230-0359
DEQ 15-2008, f. & cert. ef 12-31-08

Stat. Auth.: ORS 468.020

Stats. Implemented: ORS 468A.025