Or. Admin. Code § 340-240-0420 - Requirement for Operation and Maintenance Plans
(1) With the exception of basic and general
permit holders, a permit holder must prepare and implement operation and
maintenance plans for non-fugitive sources of particulate matter.
(2) The purposes of the operation and
maintenance plans are to:
(a) Reduce the
number of upsets and breakdowns in particulate control devices;
(b) Reduce the duration of upsets and
downtimes; and
(c) Improve the
efficiency of control devices during normal operations.
(3) The operation and maintenance plans must
consider, but not be limited to, the following:
(a) Personnel training in operation and
maintenance;
(b) Preventative
maintenance procedures, schedule and records;
(c) Logging of the occurrence and duration of
all upsets, breakdowns and malfunctions which result in excessive emissions;
(d) Routine follow-up evaluation
of upsets to identify the cause of the problem and changes needed to prevent a
recurrence;
(e) Periodic source
testing of pollution control units as required by a permit;
(f) Inspection of internal wear points of
pollution control devices during scheduled shutdowns; and
(g) Inventory of key spare parts.
NOTE: This rule is included in the State of Oregon Clean Air Act Implementation Plan that EQC adopted under OAR 340-200-0040.
Notes
Stat. Auth.: ORS 468.020, 468A.025 & 468A.050
Stats. Implemented: ORS 468.020, 468A.025 & 468A.050
State regulations are updated quarterly; we currently have two versions available. Below is a comparison between our most recent version and the prior quarterly release. More comparison features will be added as we have more versions to compare.
No prior version found.