Or. Admin. Code § 340-245-0130 - Risk Reduction Requirements
(1) A Risk Reduction Plan for an existing
source must do the following within the specified period of time under OAR
340-245-0030, as applicable:
(a) Reduce risk to less than or equal to the
TBACT Level;
(b) Require the owner
or operator to meet TBACT on all significant TEUs;
(c) Reduce risk to less than or equal to the
Risk Reduction Level; or
(d) Reduce
risk to less than or equal to the Community Engagement Level if the owner or
operator voluntarily agrees to do so.
(2) Risk Reduction Plan Requirements. The
owner or operator that is requesting approval of a Risk Reduction Plan must
submit to DEQ the following:
(a) Two air
contaminant emissions inventories:
(A) The
emissions inventory for the source submitted under OAR
340-245-0040(1)
before implementation of the proposed Risk Reduction Plan measures;
and
(B) A projected emissions
inventory for the source submitted under OAR
340-245-0040(1)
after implementation of the proposed Risk Reduction Plan measures;
(b) The results of a risk
assessment performed under OAR
340-245-0050(10) or
(11) including the risk calculations before
and after full implementation of the Risk Reduction Plan using the emissions
inventories required in subsection (a);
(c) An analysis of pollution prevention
measures under OAR 340-245-0140, and a description
of those measures that the owner or operator has undertaken and included as
part of its Toxic Air Contaminant Permit Addendum application;
(d) Identification of each TEU for which an
action will be taken to reduce risk, how the risk will be reduced, and for TEUs
that are required to meet TBACT:
(A) A
demonstration that all significant TEUs at the source meet TBACT under OAR
340-245-0220; or
(B) The TBACT analysis under OAR
340-245-0220 that demonstrates
that all significant TEUs at the source will meet TBACT when the plan is fully
implemented;
(e) A
schedule for implementing the proposed Risk Reduction Plan measures within the
time frames allowed under section (4), if not sooner. The schedule must
specify:
(A) The dates by which the source
will implement the proposed Risk Reduction Plan measures;
(B) The dates for submittal of periodic
reports showing progress toward completion of the proposed Risk Reduction Plan
measures. Progress reports should include achievement of significant
milestones, including but not limited to dates of equipment delivery and
construction progress; and
(C) The
dates for submittal of applications for permits to construct or modify, which
must be no later than 90 days after DEQ approval of the Risk Reduction Plan, or
other time period approved by DEQ;
(f) The proposed Source Risk
Limits.
(3) The owner or
operator may request a postponement of risk reduction for excess cancer and
chronic noncancer risk under OAR
340-245-0150.
(4) Risk Reduction Plan implementation
deadlines.
(a) Chronic risk. The owner or
operator of a source that has either or both an excess cancer or chronic
noncancer source risk that is greater than the TBACT Level must complete
implementation of the Risk Reduction Plan within two years from the effective
date of the Toxic Air Contaminant Permit Addendum or the operating permit with
conditions in compliance with this division, or at an earlier time as required
by DEQ in such addendum or operating permit;
(A) Except as provided in paragraph (B), the
owner or operator may apply for a permit modification as specified under OAR
340-245-0100(8)
to request additional time to complete implementation of risk reductions
measures. If the owner or operator, in such application, shows good cause for
the modification based on unreasonable hardship to the source, then DEQ may
allow the owner or operator not more than two additional years beyond the
timeline established in subsection (4)(a).
(B) DEQ may not grant a request under
paragraph (A) to an owner or operator that has previously received approval for
a postponement of risk reduction under OAR
340-245-0150;
(b) Acute risk. The owner or
operator of a source that has acute risk that is greater than the TBACT Level
must complete implementation of the Risk Reduction Plan on the following
timeline:
(A) Within one month from the
effective date of the Toxic Air Contaminant Permit Addendum or the operating
permit with conditions in compliance with this division; or
(B) If the owner or operator requests
additional time in its Toxic Air Contaminant Permit Addendum application and
shows good cause based on unreasonable hardship to the source and an evaluation
of health factors, including but not limited to severity of acute health
effect, degree of scientific certainty, and averaging time of the acute TRV
used to develop the RBC, then DEQ may allow the owner or operator up to and not
more than 12 months to complete implementation of the Risk Reduction
Plan.
(5)
Reporting Requirements.
(a) The owner or
operator of a source that has been issued a Toxic Air Contaminant Permit
Addendum or operating permit that includes a Risk Reduction Plan must submit
twice-annual progress reports to DEQ describing the source's progress in
reducing toxic air contaminant emissions and risk by implementing the Risk
Reduction Plan. The progress reports are due to DEQ on or before February 15
and July 31 of each year that the Risk Reduction Plan is in effect, or other
dates specified in the Toxic Air Contaminant Permit Addendum or operating
permit. The progress reports must include all information required by the Toxic
Air Contaminant Permit Addendum or operating permit, including but not limited
to:
(A) The increments of progress achieved in
implementing the risk reduction measures specified in the Risk Reduction
Plan;
(B) A schedule indicating
dates for future increments of progress;
(C) A description of any increases or
decreases in emissions of toxic air contaminants that have occurred at the
source since approval of the Risk Reduction Plan; and
(D) An estimate of when all Risk Reduction
Plan elements will be completed;
(b) The owner or operator must submit a Risk
Reduction Plan completion report to DEQ no later than 60 days after completing
all Risk Reduction Plan requirements. The report must include:
(A) The final increments of progress achieved
in fully implementing the risk reduction measures specified in the Risk
Reduction Plan and the date the final increments of progress were
achieved;
(B) A summary of the
actions taken to implement the Risk Reduction Plan;
(C) The results of the demonstration of the
effectiveness of the Risk Reduction Plan measures, including verification of
the modeling parameters for all of the TEUs for which risk was reduced;
and
(D) The remaining source risk
after completion of all risk reduction measures.
(6) Voluntary Risk Reductions. DEQ
will not conduct community engagement public meetings, as described in OAR
340-245-0120(3),
for the owner or operator of an existing source whose risk is less than or
equal to the TBACT Level and that agrees to voluntarily reduce risk to below
the Community Engagement Level in compliance with the following requirements:
(a) Voluntary Risk Reduction Plan. An owner
or operator must submit for DEQ approval a Voluntary Risk Reduction Plan that
follows the requirements and procedures in this rule for submittal of a Risk
Reduction Plan to reduce risk to below the Community Engagement
Level;
(b) The owner or operator
must complete implementation of the Voluntary Risk Reduction Plan within the
following timelines:
(A) Chronic risk.
(i) Two years from the effective date of the
Toxic Air Contaminant Permit Addendum, or at an earlier time as required by DEQ
for excess cancer and noncancer chronic risk; and
(ii) If additional time is needed to
implement the risk reduction measures, the owner or operator must apply for a
permit modification as specified under OAR
340-245-0100(8).
If the owner or operator shows good cause for the modification based on
unreasonable hardship to the source then DEQ may allow the owner or operator
not more than two additional years beyond the initial two years to complete
implementation of the voluntary risk reduction measures.
(B) Acute risk.
(i) One month from the effective date of the
Toxic Air Contaminant Permit Addendum for acute risk; and
(ii) If additional time is needed to
implement the risk reduction measures, the owner or operator must apply for a
permit modification as specified under OAR
340-245-0100(8).
If the owner or operator shows good cause based on unreasonable hardship to the
source and an evaluation of health factors, including but not limited to
severity of acute health effect, degree of scientific certainty, and averaging
time of the acute TRV used to develop the RBC, then DEQ may allow the owner or
operator up to and not more than 12 months to complete implementation of the
voluntary risk reduction measures; and
(c) If the owner or operator does not
complete implementation of the Voluntary Risk Reduction Plan within the
approved time, DEQ may initiate the community engagement requirements under OAR
340-245-0120.
(7) Immediate Curtailment Risk
Reduction Plan. If the results of the DEQ approved Level 3 or Level 4 Risk
Assessment, submitted under OAR
340-245-0050, demonstrate source
risk is greater than the Immediate Curtailment Level in OAR
340-245-8010 Table 1, the owner
or operator must:
(a) Submit to DEQ, by the
deadline provided in OAR
340-245-0030(1)(e),
an Immediate Curtailment Risk Reduction Plan that describes the actions the
source will take to immediately reduce risk below the Immediate Curtailment
Level. The Immediate Curtailment Risk Reduction Plan must include:
(A) Specific actions to immediately reduce
risk from Significant TEUs, which may include:
(i) Production activity reductions or process
modifications;
(ii) Material
substitution or product reformulation;
(iii) Additional operations and maintenance;
and
(iv) Improvements to, or
installation of, pollution control devices;
(B) The amount of risk reduction anticipated
from the actions included under paragraph (A) and all supporting estimation
methods and calculations; and
(C)
Monitoring procedures to ensure the anticipated reduction amounts in paragraph
(B) are achieved;
(b)
Fully implement the Immediate Curtailment Risk Reduction Plan within ten days
of DEQ approval of the plan.
(8) If the owner or operator submits an
incomplete Immediate Curtailment Risk Reduction Plan or if DEQ determines that
the Immediate Curtailment Risk Reduction Plan is inadequate, then in addition
to any other remedies available to DEQ, including authority pursuant to ORS
468.115, if applicable, DEQ may
modify the Immediate Curtailment Risk Reduction Plan and order the owner or
operator to comply with such plan. The owner or operator must fully implement
the modified Immediate Curtailment Risk Reduction Plan within 10 days of
receipt.
(9) The owner or operator
must comply with the Immediate Curtailment Risk Reduction Plan until:
(a) DEQ issues a Toxic Air Contaminant Permit
Addendum under OAR 340-245-0100 with an approved
Risk Reduction Plan; and
(b) The
owner or operator implements the approved Risk Reduction Plan.
Notes
Statutory/Other Authority: ORS 468.020, 468.065, 468A.025, 468A.040, 468A.050, 468A.070, 468A.155, 468A.135 & 468A.337
Statutes/Other Implemented: 468.065, 468A.025, 468A.040, 468A.050, 468A.070, 468A.155, 468A.010, 468A.015, 468A.035, 468A.337 & 468A.335
State regulations are updated quarterly; we currently have two versions available. Below is a comparison between our most recent version and the prior quarterly release. More comparison features will be added as we have more versions to compare.
No prior version found.