Or. Admin. Code § 340-245-9020 - Colored Art Glass Manufacturing Facility Rules; Permit Required
(1) Not later than
December 1, 2016, if located within the Portland AQMA, and not later than April
1, 2017, if located outside the Portland AQMA, all CAGMs not otherwise subject
to a permitting requirement must apply for a permit under OAR
340-216-8020 Table 2, Part B,
category #84.
(2) A CAGM that
applies for a permit on or before the required date is not in violation of OAR
340-216-0020(3).
(3) CAGMs constructed after September 1, 2016
must obtain a permit prior to construction.
NOTE: This rule was moved verbatim from OAR 340-244-9020 and renumbered.
Notes
Statutory/Other Authority: ORS 468.020, 468A.025 & 468A.040
Statutes/Other Implemented: 468A.025 & 468A.040