Or. Admin. Code § 340-271-0330 - Compliance with a BAER Order
(1)
The owner or operator of a covered stationary source for which DEQ has issued a
BAER order according to OAR
340-271-0320 must:
(a) Comply with the requirements in the BAER
order; and
(b) For an existing
source that is required to complete a BAER assessment under OAR
340-271-0310(1)(a),
submit to DEQ or LRAPA, as applicable, a complete permit modification
application for a CPP permit addendum according to OAR
340-271-0150(3)
not later than 90 days after the date that the BAER order is final and
effective, or a later date specified in the BAER order.
(2) Reporting requirements.
(a) The owner or operator of a covered
stationary source that has been issued a CPP permit addendum or operating
permit that includes provisions related to a BAER order must submit an annual
progress report to DEQ describing the progress in implementing the requirements
in the BAER order. The annual progress reports are due to DEQ on or before
February 15 of each year following the date that the notice of the BAER order
is final and effective. The annual progress report must include:
(A) A description of the progress achieved in
implementing the requirements in any BAER order;
(B) A schedule indicating dates for future
increments of progress;
(C) A
description of any increases or decreases in covered emissions that have
occurred at the covered stationary source since the submission date of the most
recently conducted complete BAER assessment; and
(D) An estimate of when all implementation of
requirements of the BAER order will be complete.
(b) The owner or operator of a covered
stationary source must submit a BAER order completion report to DEQ no later
than 60 days after implementation of all requirements in the BAER order are
complete, except for items related to continuous and ongoing requirements. The
report must include:
(A) The final increments
of progress achieved in fully implementing the requirements in the BAER order
and the date the final increments of progress were achieved;
(B) A summary of the actions taken to fully
implement the requirements in the BAER order; and
(C) An estimate of the resulting covered
emissions reductions that will be achieved now that the requirements in the
BAER order are being implemented.
Notes
Statutory/Other Authority: ORS 468.020, 468A.025 & 468A.040
Statutes/Other Implemented: ORS 468.020, 468A.025, 468A.040, 468.035, 468A.010, 468A.015 & 468A.045