Or. Admin. Code § 345-024-0503 - Definitions for OAR 345-024-0500 to 345-024-0720
In OAR 345-024-0500 to 345-024-0720, unless the context requires otherwise terms have the meaning provided in ORS 469.300, 469.503(2)(e) and the following definitions:
(1)
"Gross carbon dioxide emissions" as defined in ORS
469.503(2)(e).
The Council must measure the gross carbon dioxide emissions of a fossil-fueled
power plant on a new and clean basis. For nongenerating energy facilities that
emit carbon dioxide, the Council must measure the gross carbon dioxide
emissions as described in OAR
345-024-0620(1).
(2) "Natural gas-fired facility" means an
energy facility that is intended to be fueled by natural gas except for
infrequent periods when the natural gas supply is interrupted, during which an
alternate fuel may be used. Such alternate fuel use may not exceed 10 percent
of expected fuel use in British thermal units, higher heating value on an
annual basis.
(3) "New and clean
basis" means the average carbon dioxide emissions rate per hour and net
electric power output of the energy facility, without degradation. The site
certificate holder must determine the new and clean basis:
(a) By a 100-hour test at full power that the
site certificate holder completes during the first 12 months of commercial
operation of the energy facility, unless the Council specifies a different
testing period for a non-base load power plant (or power augmentation) or a
nongenerating energy facility. A 100-hour test performed for purposes of the
certificate holder's commercial acceptance of the facility may suffice in lieu
of testing after beginning commercial operation;
(b) With the results adjusted for the average
annual site condition for temperature, barometric pressure and relative
humidity and use of alternative fuels unless the Council specifies that the
results for a non-base load power plant (or power augmentation) or a
nongenerating energy facility be adjusted for the average temperature,
barometric pressure and relative humidity at the site during the times of the
year when the facility is intended to operate;
(c) Using a rate of 117 pounds of carbon
dioxide per million Btu of natural gas fuel (higher heating value);
and,
(d) Using a rate of 161 pounds
of carbon dioxide per million Btu of distillate fuel (higher heating value), if
such fuel use is proposed by the applicant.
(e) Notwithstanding subsection (a) and
including subsections (b) through (d), for a facility that employs major power
generating equipment that has previously been used, the new and clean basis
means the average carbon dioxide emissions rate and net electric power output
for the first use of the equipment at the site, as determined by historical
data from the previous usage or by testing on site.
(4) "Non-base load power plant" means a
fossil-fueled generating facility that is limited by the site certificate to an
average number of hours of operation per year of not more than 6,600 hours. For
a non-base load power plant designed to operate at variable loads, the
facility's annual hours of operation are determined by dividing the actual
annual electric output of the facility in megawatt-hours by the facility's
nominal electric generating capacity in megawatts. The Council will assume a
30-year life for the plants for purposes of determining gross carbon dioxide
emissions, unless the applicant requests and the Council approves a shorter
operational life in the site certificate. If the Council approves a shorter
operational life, the certificate holder must operate the facility for no
longer than the approved operational life or, before the expiration of the
approved operational life, must request an amendment of the site certificate to
extend the operational life.
(5)
"Offset funds" means the amount of funds determined by the Council to satisfy
the applicable carbon dioxide emissions standard pursuant to OAR
345-024-0560(3),
345-024-0600(3)
or 345-024-0630(2) and
(4).
(6) "Power augmentation" means technologies
that increase the capacity and the heat rate of the plant above the capacity
and heat rate of the base load gas plant. These include, but are not limited
to, duct burning and some forms of steam augmentation.
Notes
Statutory/Other Authority: ORS 469.470
Statutes/Other Implemented: ORS 469.413, 469.501 & 469.503