Or. Admin. Code § 345-027-0385 - Request for Amendment to Extend Construction Deadlines
(1) The certificate holder may request an
amendment to the site certificate to extend the deadlines for beginning or
completing construction of the facility, or portion/phase of the facility, that
the Council has approved in a site certificate or an amended site certificate
by submitting a preliminary request for amendment in accordance with OAR
345-027-0360. The preliminary
request for amendment must include an explanation of the need for an extension
and must be submitted to the Department before the applicable construction
deadline, but no earlier than the date twelve months before the applicable
construction deadline.
(2) A
preliminary request for amendment received by the Department within the time
allowed under section (1) of this rule to extend the deadlines for beginning
and completing construction suspends expiration of the site certificate or
amended site certificate until the Council acts on the request for amendment.
If the Council denies the extension request after the applicable construction
deadline, the site certificate is deemed expired as of the applicable
construction deadline specified in the site certificate or amended site
certificate.
(3) If the Council
grants an amendment under this rule, the Council must specify new deadlines for
beginning or completing construction that are the later of:
(a) Three years from the deadlines in effect
before the Council grants the amendment; or
(b) Following a contested case proceeding
conducted pursuant to OAR
345-027-0371, two years from the
date the Council grants the amendment.
(4) For requests for amendment to the site
certificate received under this rule to extend construction deadlines for
facilities or portions of the facility the Council may not grant more than two
amendments to extend the deadline for beginning construction of a facility or a
phase of a facility.
(5) For
requests for an amendment to the site certificate to extend construction
deadlines for facilities, or portions/phases of facilities, not yet in
construction, but already approved for construction in the site certificate or
amended site certificate prior to October 24, 2017:
(a) Sections (1) and (2) of this rule
apply;
(b) Sections (3) and (4) of
this rule do not apply;
(c) When
considering whether to grant a request for amendment for a deadline extension
made under this section, the Council must consider how many extensions it has
previously granted; and
(d) If a
request for amendment for a deadline extension made under this section is
granted, the Council must specify new deadlines for beginning or completing
construction that are not more than two years from the deadlines in effect
before the Council grants the amendment.
Notes
Statutory/Other Authority: ORS 469.470
Statutes/Other Implemented: ORS 469.370, 469.405 & 469.503