Or. Admin. Code § 350-082-0460 - Resource Enhancement Projects
(1) Resource enhancement projects may be
allowed where authorized in specified land use designations and consistent with
the guidelines in sections (2) through (6) below.
(2) Applications for resource enhancement
projects must describe the goals and benefits of the proposed enhancement
project. They must also thoroughly document the condition of the resource
before and after the proposed enhancement project. Applicants shall seek
technical assistance from federal, state or county technical experts for
assistance in designing voluntary wetland, stream, habitat, plant, and scenic
enhancement projects.
(3) In
addition to compliance with 350-0872-0600 through
350-082-0720, quarry enhancement
projects shall comply with the following guidelines:
(a) Application Requirements. In addition to
other applicable requirements, land use applications for quarry enhancement
projects shall include perspective drawings of the site as visible from key
viewing areas as specified in
350-082-0500(6)(f)
and a reclamation plan that provides at a minimum the following information:
(A) A map of the site, at a scale of one inch
equals 200 feet (1:2,400) or a scale providing greater detail, with 10-foot
contour intervals or less, showing pre-reclamation existing grades and
post-reclamation final grades; locations of topsoil stockpiles for eventual
reclamation use; location of catch basins or similar drainage and erosion
control features employed for the duration of the use; and the location of
storage, processing, and equipment areas employed for the duration of the
use.
(B) Cross-sectional drawings
of the site showing pre-reclamation and post- reclamation grades.
(C) Descriptions of the proposed use, in
terms of estimated quantity and type of material removed, estimated duration of
the use, processing activities, etc.
(D) Description of drainage and erosion
control features to be employed for the duration of the use.
(E) A landscaping plan providing for
revegetation consistent with the vegetation patterns of the subject landscape
setting, indicating the species, number, size, and location of plantings for
the final reclaimed grade, as well as a description of irrigation provisions or
other measures necessary to ensure the survival of plantings.
(b) Scenic Resource Standard.
Quarry enhancement projects shall restore the site to a natural appearance that
blends with and emulates surrounding landforms to the maximum extent
practicable.
(c) Natural Resource
Standard. Sites shall be replanted using native plants found in the landscape
setting or ecoregion to the maximum extent practicable.
(d) Time Frames. The following time frames
shall apply to quarry enhancement projects:
(A) All grading (e.g., excavating, filling
and re-contouring) shall be completed within one year of the date an applicant
begins on-the-ground work.
(B) All
landscaping shall be planted within one year of the date an applicant completes
the grading.
(C) An applicant may
request one one-year extension to the one-year grading time frame if a project
is unexpectedly delayed by adverse weather or emergency/disaster. Such requests
shall be considered an administrative action. An applicant shall submit such a
request to the reviewing agency after grading has commenced and before the
one-year grading time frame has expired.
(D) An applicant may also request one
six-month extension to the one-year landscaping time frame if a project is
unexpectedly delayed by adverse weather or emergency/disaster. Such requests
shall be considered an administrative action. An applicant shall submit such a
request to the reviewing agency after landscaping has commenced and before the
one-year landscaping time frame has expired.
(4) Enhancement of wetlands not associated
with any other project proposal may be allowed, if such efforts are conducted
pursuant to a written plan consistent with
350-082-0640(7).
(5) Enhancement of streams, ponds, lakes, and
riparian areas not associated with any other development proposal may be
allowed, if such efforts are conducted pursuant to a written plan consistent
with 350-082-0640(8).
(6) In the SMAs, enhancement of water
resources not associated with any other project proposal may be allowed, if
such efforts comply with the water resources provisions in the Management Plan.
Enhancement efforts shall be conducted pursuant to a written plan, consistent
with 350-082-0670(2).