Or. Admin. Code § 350-082-0540 - Renewable Energy Production in the GMA
(1) Renewable energy production may be
allowed where authorized in specified land use designations and consistent with
the guidelines in sections (2) through (5) below.
(2) Except as specified in section (3) below,
production of electrical power, including, but not limited to wind and solar
production, for commercial purposes is considered an industrial use and is
prohibited.
(3) Solar and wind
power generation that is accessory to a primary structure or allowed use in the
GMA is not considered an industrial use and may be permitted provided that the
capacity for power generation is limited to the expected annual electrical
power need of the structure or use. The generating equipment may serve only the
parcel on which it is located, or an adjacent parcel in the same ownership and
used in conjunction with the subject parcel. Sale of power back to the
electrical grid is permitted, provided that it is an occasional event, not
ongoing over the course of the year.
(4) Equipment attached to an existing
structure is an addition to the structure on which it is located.
(5) Free-standing equipment is a new
accessory structure.