Or. Admin. Code § 581-022-2223 - Healthy and Safe Schools Plan
(1)
The following definitions apply to this rule:
(a) "Department" means the Oregon Department
of Education;
(b) "District" or
"School District" means school districts as defined by ORS Chapter
332;
(c) "Education Service
District" or "ESD" means an education service district as defined by ORS
Chapter 334;
(d) "Electronic
Communications Program" means a program or service that allows a School
District, Public Charter School or Education Service District to send out
electronic communications and email to multiple recipients at once;
(e) "Facilities" means all buildings or
properties owned or leased by a District, ESD, or Charter School that are
required to be included in the HASS Plan;
(f) "Final Test Results" means final test
results for any test required as part of the Healthy and Safe Schools Plan that
contains the results from the appropriate laboratory as well as enough
additional information to contextualize and explain the laboratory
results;
(g) "Healthy and Safe
Schools Plan" or "HASS Plan" means a plan that complies with all requirements
in ORS 332.331;
(h) "OHA" means the Oregon Health
Authority;
(i) "Public Charter
School" or "Charter School" means a charter school as defined by ORS Chapter
338;
(j) "Required Fixtures" means
fixtures required to be tested for elevated levels of lead per OAR
333-061-0400; and
(k) "Testing
Cycle" means a six year cycle, as required per OAR 333-061-0400 in which School
Districts, Education Service Districts and Public Charter Schools test all
Required Fixtures in all Facilities for elevated levels of lead.
(2) The Department shall publish
on its website, and send out via electronic means, a copy of model HASS Plans
to Districts, ESDs, and Charter Schools by January 1, 2019.
(3) The model HASS Plan shall:
(a) Contain language that Districts, ESDs,
and Charter Schools may adopt in creating their HASS Plans;
(b) Contain all elements required under ORS
332.331; and
(c) Contain instructions to enable Districts,
ESDs, and Charter Schools to complete their HASS Plans according to the model
plan.
(4) Districts,
ESDs, and Charter Schools shall submit an electronic copy of a draft HASS Plan
to the Department by April 1, 2019.
(5) The draft HASS Plan submitted by
Districts, ESDs, and Charter Schools, shall:
(a) Contain all requirements listed in ORS
332.331; and
(b) Provide a schedule of when the District,
ESD, or Charter School will test Required Fixtures for each Facility based on
the schedule set forth in this rule.
(6) The Department shall review draft model
plans and report their results back to Districts, ESDs, and Charter
Schools.
(7) The governing body of
a District, ESD, or Charter School shall adopt the final HASS Plan by July 1,
2019.
(8) Districts, ESDs, and
Charter Schools must submit an electronic copy of their adopted HASS Plan to
the Department by July 15, 2019.
(9) If a District, ESD, or Charter School has
a change in Facilities, personnel, policies and procedures, or any other
change, which requires updating their HASS Plan, the District, ESD, or Charter
School shall submit an electronic copy of the revised HASS Plan to the
Department by June 1 of the school year in which the revisions
occurred.
(10) By January 1, 2019,
the Department shall publish on its website and distribute an electronic copy
of a model annual statement required by ORS
332.334 to Districts, ESDs, and
Charter Schools.
(11) By June 1 of
each year, Districts, ESDs, and Charter Schools shall submit an electronic copy
of their annual statement to the Department and all others required by ORS
332.334.
(12) Districts, ESDs, and Charter Schools
that have email addresses for parents of minor students and students over 18
years of age may email them the annual certification.
(13) Districts, ESDs, and Charter Schools
that use an electronic communications program, in place of an email list, to
send regular communications to members of their community may use that program
to provide Final Test Results as part of a regular communication to members of
the community.
(14) If the
electronic communication programs allow the District, ESD or Charter School to
specify which community members receive an email communication, then school
districts, education service districts, or public charter schools may limit who
receives the communication of Final Test results of a specific building so long
everyone connected with that building receives the required notice.
(15) The Department shall reimburse
Districts, ESDs, and Charter Schools that complete initial testing between July
1, 2019 and June 30, 2020 for testing costs as stated in subsections (17)(a)
through (c) of this rule plus an additional ten dollars.
(16) All Districts, ESDs, and Charter Schools
must test all Required Fixtures for elevated levels of lead every 6 years
starting July 1, 2020 per OAR 333-061-0400.
(17) The Department shall reimburse districts
for the following costs:
(a) Actual testing
of water samples for elevated levels of lead, as evidenced by invoices from an
OHA accredited lab;
(b) Shipping
costs to send samples to an OHA accredited lab;
(c) Costs of supplies needed to collect
samples; and
(d) An additional
amount to be determined by the Department that:
(A) Provides as practical as possible an
equal amount per sample across all tests; and
(B) Help districts offset some of the costs
of collecting the samples and associated administrative costs.
(18) The Department may
reimburse Districts, ESDs, and Charter Schools for testing done on fixtures in
addition to the testing done on Required Fixtures. The additional reimbursement
shall be at the discretion of the Department and the Department shall consider:
(a) Total available funds for reimbursement;
and
(b) Total additional tests
done.
(19) Districts and
ESDs shall use the following schedule for testing through the Testing Cycle:
(a) Districts with 1-3 schools within their
district will test all Required Fixtures in the first year of the Testing
Cycle;
(b) Districts with 4-6
schools within their district will test all Required Fixtures in the second
year of the Testing Cycle;
(c) ESDs
will test all Required Fixtures in the third year of the Testing
Cycle;
(d) Districts with 7-8
schools within their district will test all Required Fixtures in the third and
fourth years of the Testing Cycle;
(e) Districts with 9-10 schools within their
district will test all Required Fixtures in the fifth and sixth years of the
Testing Cycle;
(f) Districts with
11-12 schools within their district will test all Required Fixtures in the
fourth, fifth, and sixth years of the Testing Cycle;
(g) Districts with 13-15 schools within their
district will test all Required Fixtures in the fourth, fifth, and sixth years
of the Testing Cycle;
(h) Districts
with 16-20 schools within their district will test all Required Fixtures in the
third, fourth, fifth, and sixth years of the Testing Cycle;
(i) Districts with over 20 schools within
their district will test a portion of all Required Fixtures in each year of the
Testing Cycle;
(20)
Charter Schools will test all Required Fixtures according to the testing
schedule for the district in which they are located.
(21) Districts and Charter Schools that have
multiple years to test all Required Fixtures shall report in their HASS Plans
when each Facility will be tested.
(22) The Department shall approve District,
ESD, and Charter School schedules.
(23) If the Department does not approve a
schedule, the District, ESD, or Charter School shall resubmit their
schedule.
(24) The Department may
determine a schedule for when Districts, ESDs, and Charter Schools must submit
their reimbursement requests.
(25)
The Department may require Districts, ESDs, and Charter Schools to report data
using reimbursement templates and forms developed by the Department for this
purpose.
Notes
Statutory/Other Authority: ORS 326.051, ORS 332.331 & 332.334
Statutes/Other Implemented: ORS 332.331 & 332.334
State regulations are updated quarterly; we currently have two versions available. Below is a comparison between our most recent version and the prior quarterly release. More comparison features will be added as we have more versions to compare.
No prior version found.