(1) The Department
will review applications to ensure they are complete and meet the requirements
in OAR 603-007-0031. The Department may request additional
information.
(2) After review, the
Department will approve those applications that meet eligibility requirements
based on funding limitations in OAR 603-007-0041.
(3) The Department may conduct additional
rounds of open application periods, if necessary, based on funding
availability.
(4) After reviewing
the applications, the Department may award remaining available funds to all
grantees through a grant amendment.
(a) The
Department will award remaining available funds no later than June 27, 2025, at
a proportionate rate not to exceed a grantee's total project costs,
notwithstanding payment limitations under OAR 603-007-0041.
(b) The Department may give additional
consideration to projects that meet requirements under one or more of the
following categories:
(A) Air quality and
temperature control;
(B) Water
systems, including those serving cooking and bathroom facilities; and
(C) Electrical infrastructure.
Notes
Statutory/Other Authority: HB 2001 (2023)
Statutes/Other Implemented: HB 2001 (2023)
State regulations are updated quarterly; we currently have two versions available. Below is a comparison between our most recent version and the prior quarterly release. More comparison features will be added as we have more versions to compare.
No prior version found.