Or. Admin. Code § 635-425-0040 - Notification Requirements
(1)
Applicants must notify the district fishery or habitat biologist at least 48
hours before actual blasting, and the Department must have the opportunity to
have an observer present during and after the blasting. The Department may
conduct a pre-blasting site inspection.
(2) Applicants must notify the local law
enforcement agencies before blasting activities.
(3) Applicants must notify all adjacent
landowners of record on the most recent property tax assessment roll, renters
or lessees, and recreational users within the area affected by the proposed
blasting of the schedule for planned in-water blasting. This notice must be by:
(a) Registered letters to adjacent landowners
with return receipt;
(b)
Publication in the local newspaper;
(c) Postings in the vicinity of the project;
and
(d) Auditory warnings before
blasting.
(4) The
applicant must provide to the Department satisfactory evidence of compliance
with subsections (3)(a)-(c) of this rule at least three days before the
blasting occurs.
Notes
Stat. Auth.: ORS 496.012, ORS 496.138, ORS 496.146, ORS 506.109,ORS 506.119 & ORS 509.140
Stats. Implemented: ORS 496.012, ORS 496.138, ORS 496.146, ORS 506.109, ORS 506.119 & ORS 509.140