Or. Admin. Code § 690-020-0140 - Modification of Dams
(1) No person
shall make Modifications to a Dam unless the State Engineer has reviewed all
required documents as described in this section and has approved those
documents as indicated in written communication with the Engineer of Record or
Dam owner.
(2) The following Dam
Modifications require State Engineer approval of plans:
(a) Changes to or near the Spillway that may
affect Spillway capacity or ability to pass flows safely;
(b) Placing, replacing, or relining any
Conduit within the Dam;
(c) Removal
or alteration of the Conduit control structure;
(d) Installation of a new Valve on the
downstream side of the low level Conduit;
(e) Correction of damage where that damage
has impacted the safe functioning of the Dam;
(f) Any activity where 10 percent or more of
the fill material in the Dam is disturbed; or
(g) Any other change to the Dam that results
in a Modification as defined in OAR 690-020-0022(28).
(3) Dam Modification plans shall include all
details of the area of the Dam being modified. Specific modification plan
requirements include, but are not limited to:
(a) For major Spillway damage or alteration,
plans need to address passage of the required Inflow Design Flood based on the
Hazard Rating of the Dam, with the same criteria as required for new Dams in
OAR 690-020-0037;
(b) For
stabilization of slope movement, plans require slope stability analysis and
appropriate corrective measures;
(c) For replacement of Conduits or
installation of a Valve on the downstream side of a Dam, plans require an
analysis of internal erosion potential;
(d) For internal erosion, plans must address
construction of a filter zone; and
(e) Items required by the State Engineer
pursuant to subsection (4).
(4) The Dam owner shall provide sufficient
notice to the Department to allow for adequate time for discussion of the
proposed Modifications and the necessary design requirements.
(5) The State Engineer will determine the
design and submittal requirements. Submittal requirements and Department
reviews may be expedited in the event of emergency or unanticipated
weather-related situations.
(6)
Water is not to be stored in the reservoir during modification. The Engineer of
Record may propose maintaining some Water in storage during Dam Modification or
modifying Dam Height if it is demonstrated that it can be done in a manner that
protects life, property, and infrastructure. The Department will review
submitted materials for the proposed construction actions. The Department may
consider the scope of the project, including how the proposed construction
actions will maintain safe Water levels through the duration of
construction.
Notes
Statutory/Other Authority: ORS 536.027, 540.488
Statutes/Other Implemented: ORS 540.443, 540.449, 540.488