Or. Admin. Code § 690-601-0500 - Application Requirements and Evaluation of Community Engagement Plans
(1) Community engagement plan applicants
shall comply with all the application requirements pursuant to ORS
541.561-541.581 or ORS 541.651 - 541.696.
(2) Community engagement plan applicants,
within loan or grant applications, may propose not to incorporate one or more
of the Department recognized best practices in community engagement plans for a
water project. If a community engagement plan applicant seeks not to
incorporate one or more Department recognized best practices, then:
(a) The community engagement plan applicant
shall provide evidence to the Department explaining why the recognized best
practice does not meet the community engagement plans desired outcomes or
advance disproportionately impacted community involvement.
(b) The Department shall determine whether
the recognized best practice should be used, waived, or replaced with an
alternative best practice proposed by the community engagement plan applicant.
If the Department determines that the recognized best practice shall be
replaced by an alternative best practice, then:
(A) The community engagement plan applicant
shall provide evidence to the Department showing that the proposed alternative
meets the community engagement plans desired outcomes or advances
disproportionately impacted community involvement.
(B) The Department shall determine whether
these alternative practices can replace a Department recognized best practice
in the community engagement plan. In assessing alternatives, the Department may
consider, but is not limited to, size and scope of the water project and the
identified needs of the disproportionately impacted community.
(3) The Department
shall evaluate the community engagement plan components of an application
according to relevant evaluation criteria in ORS 541.561-541.581 or ORS 541.651 - 541.696, and community engagement plan components described in OAR
690-601-0004(1) and OAR 690-601-0004(2).
(4) The Department may evaluate the community
engagement plan components of an application to ORS 541.561-541.581 or ORS
541.651 - 541.696 on additional criteria including but not limited to:
(a) Significance and impact of the water
project and community engagement plan on local communities and
disproportionately impacted communities.
(b) Appropriateness of the budget and the
resources involved in the community engagement plan to increase meaningful
involvement of local communities and disproportionately impacted communities in
the water project.
(c) Expertise,
qualifications, and level of community connections held by the local
governments or local organizations involved in the community engagement
plan.
(5) The Department
may deny funding of a community engagement plan if the Community Engagement
Plan Applicant fails to comply with any item described in OAR 690-601-0400(1)
and OAR 690-601-0400(2).
Notes
Statutory/Other Authority: ORS 536.027, ORS 541.561-541.581, ORS 541.651 - 541.696 & ORS 541.551
Statutes/Other Implemented: ORS 541.561-541.581, ORS 541.651 - 541.696 & ORS 541.551
State regulations are updated quarterly; we currently have two versions available. Below is a comparison between our most recent version and the prior quarterly release. More comparison features will be added as we have more versions to compare.
No prior version found.