Or. Admin. Code § 731-147-0055 - Sole-Source Procurements
(1)
Generally. ODOT may Award a Public Contract without competition as a
Sole-Source Procurement pursuant to the requirements of ORS
279B.075 and this
rule.
(2) Public Notice. If the
value of the resulting Public Contract exceeds $250,000, ODOT shall publish a
Public Notice in a manner similar to a Public Notice for a solicitation for
Competitive Sealed Bids or Competitive Sealed Proposals. The Public Notice must
describe the Goods or Services, or both, to be acquired by the Sole-Source
Procurement; identify the prospective Contractor; and state the date, time and
place that protests are due. ODOT will advertise the Public Notice at least
seven (7) Days before Award of the Contract.
(3) Protest. For Sole-Source Procurements
requiring Public Notice under this rule, an Affected Person may protest the
determination of ODOT that the Goods or Services or class of Goods or Services
are available from only one source. Pursuant to ORS
279B.420(3)(f),
before seeking judicial review, an Affected Person must file a Written protest
with ODOT and exhaust all administrative remedies.
(a) Delivery. Unless otherwise specified in
the Public Notice of the Sole-Source Procurement, an Affected Person must
deliver a Written protest to ODOT within seven (7) Days after the first date of
Public Notice of the Sole-Source Procurement, unless a different protest period
is provided in the Public Notice of a Sole-Source Procurement.
(b) Content of Protest. The Written protest
must include:
(A) A detailed statement of the
legal and factual grounds for the protest;
(B) A description of the resulting harm to
the Affected Person; and
(C) The
relief requested.
(c)
ODOT Response. ODOT shall not consider an Affected Person's Sole-Source
Procurement protest submitted after the timeline established for submitting
such protest under this rule, or such different time period as may be provided
in the Public Notice of the Sole-Source Procurement. ODOT shall issue a Written
disposition of the protest in a timely manner. If ODOT upholds the protest, in
whole or in part, the Contracting Agency shall not enter into a Sole-Source
Contract.
(d) Judicial Review.
Judicial review of ODOT disposition of a Sole-Source Procurement protest shall
be in accordance with ORS
279B.420.
Notes
Statutory/Other Authority: ORS 184.619, 279A.065(6) & 279B.075
Statutes/Other Implemented: ORS 279B.075