Or. Admin. Code § 734-010-0380 - DAS Appeal Process Covering Contractor Evaluations
(1) In the event that a contractor's
prequalification is suspended by ODOT, the contractor may appeal the suspension
to DAS in accordance with ORS
279C.445 and
279C.450. If the contractor
wishes to appeal suspension of its prequalification as a bidder to DAS, the
contractor must, within 7 business days after receipt of notice of suspension,
notify the OPO Construction Contracts Manager in writing.
(2) Upon receipt of such notice of appeal,
the OPO Construction Contracts Manager will immediately notify the Director of
DAS and the SCME.
(3) The Director
of DAS will notify the appealing party and ODOT of the time and date of the
hearing. The hearings appeal and final decision will take place in accordance
with the statutory requirements and applicable DAS rules.
(4) If the suspension is upheld, the OPO
Construction Contracts Manager will notify the contractor and the SCME that the
suspension of the contractor's prequalification will begin 10 days after the
contractor is notified.
Notes
Stat. Auth.: ORS 184.616, 184.619, 279A.050, 279A.065 & 279C.430
Stats. Implemented: ORS 279C.430
State regulations are updated quarterly; we currently have two versions available. Below is a comparison between our most recent version and the prior quarterly release. More comparison features will be added as we have more versions to compare.
No prior version found.