Or. Admin. Code § 734-024-0040 - Improving the Environmental Permitting Process
(1) The Department must consider improvements
to the environmental permitting process for state highway construction projects
in order to achieve the following outcomes:
(a) Reduce the time required to design
projects associated with meeting environmental requirements;
(b) Reduce the time required to obtain
environmental permits;
(c) Reduce
the cost and delay associated with redesigning projects to meet environmental
requirements;
(d) Maintain a strong
commitment to environmental stewardship; and
(e) Reduce this state's dependence on foreign
oil.
(2) In order to
achieve these outcomes, the Department must, but is not limited to:
(a) Work with state and federal resource and
regulatory agencies to develop programmatic agreements and permits.
(b) Develop performance measures, goals, and
improvement strategies and initiatives.
(c) Develop and publish periodic progress
reports on Department performance in achieving these environmental permit
process outcomes.
Notes
Stat. Auth.: ORS 184.616, 184.619, OL 2009, Ch. 865, sec 18
Stats. Implemented: OL 2009, Ch. 865, sec 18
State regulations are updated quarterly; we currently have two versions available. Below is a comparison between our most recent version and the prior quarterly release. More comparison features will be added as we have more versions to compare.
No prior version found.