Or. Admin. Code § 734-051-4050 - Special Use Approaches
(1)
Procedure. The region manager shall approve an application for a special use
approach where the department determines that a complete application has been
submitted pursuant to OAR
734-051-3030 and that the
approach can be operated safely. The department shall consider the spacing,
channelization and sight distance standards outlined in OAR
734-051-4020 when determining
whether an approach can be operated safely.
(2) Design. The design of special use
approaches shall:
(a) Be limited from general
use by physical means such as a gate or other design approved by the
department; and
(b) May require
special design considerations such as reinforced sidewalks, curb design
options, and landscaping considerations.
(3) Mitigation. The region manager may
require mitigation measures to be incorporated into a construction permit and a
permit to operate a special use approach.
(4) Right of Access for Special Use
Approaches. The applicant must have a right of access to apply for a special
use approach permit. Existence of a recorded easement may not by itself
establish a right of access and does not guarantee the approval of an
application for a special use approach or the location of a special use
approach.
(5) Deviations. Approval
of a deviation is not required for approval of an application for a special use
approach.
(6) Appeal. The
department's decision to deny or approve with mitigation applications under
this section are subject to post-decision review under OAR
734-051-3080.
Notes
Stat. Auth.: ORS 184.616, 184.619, 374.310-374.314, 374.345 & 374.355
Stats. Implemented: ORS 374.300-374.360, §27, ch. 330, OL 2011
State regulations are updated quarterly; we currently have two versions available. Below is a comparison between our most recent version and the prior quarterly release. More comparison features will be added as we have more versions to compare.