This rule describes the process the Department follows in completing new state park master plans and amending existing master plans. In the master planning process, the Department shall provide reports and maps as appropriate for each step of the process for agency and public examination. The Department shall:
(1) Assess the
occurrence and importance of the natural and cultural resources in the
park.
(2) Determine the suitability
of areas of the park for recreational use and development based on the natural
and cultural resource assessments and the Department's composite suitability
assessment process as defined in OAR
736-018-0020(1)(c).
(3) Assess the recreational aspects of the
park including:
(a) Current and future demand
for outdoor recreational activities and related facilities in the vicinity of
the park, and the statewide, regional and local supply of recreational
opportunities and facilities related to demanded activities;
(b) The existing recreational opportunities
and facilities in the park; and
(c)
The recreational activities and facilities that could potentially be provided
in the park.
(4) Assess
the natural, cultural, and scenic resource management and interpretive needs of
the park.
(5) Assess lands adjacent
to the park for potential impacts on park resources and for opportunities to
provide additional park resource protection or recreational
opportunities.
(6) Convene a
steering committee to review master planning work in progress. In forming the
steering committee, the Department shall invite representatives of interested
local, state and federal agencies, neighborhood interests, resource advocacy
interests, and recreation advocacy interests relevant to the park. Department
staff shall meet with, and solicit recommendations from the committee at key
times in the process.
(7) Compile a
preliminary list of issues including but not limited to the problems,
constraints, needs and opportunities related to the use, development and
interpretation of the park, protection and management of park resources, and
the need and potential for park expansion through acquisition.
(8) Present the issues and other information
and solicit comments in the following forums:
(a) At least one meeting of the steering
committee;
(b) At least one public
meeting held in the vicinity of the park and at least one other public meeting
in a location that encourages broad participation, each followed by a public
comment period of at least 21 days to provide for submittal of written
comments;
(c) Informal meetings
with Department staff and other agencies and interest groups as needed;
and
(d) At least one public meeting
of the Commission.
(9)
Formulate goals for the use, development and interpretation of the park and
management of its resources and for any potential park expansion.
(10) Prepare preliminary use and development
proposals for the park. Include descriptions of the uses or facility types,
intensities, sizes, site designs and locations and identification of any
alternative sites based on the assessments completed in sections (1) through
(6) of this rule, and considering information collected through the activities
described in sections (7) through (10) of this rule. Adjust the preliminary
proposals as needed after completion of the assessments described in sections
(13) through (15) of this rule.
(11) Prepare preliminary natural, cultural
and scenic resource management guidelines as described in OAR
736-018-0020(2)(d) through
(f).
(12) Assess local and regional transportation
system needs in relation to preliminary proposed park uses or facilities and
resource management guidelines, in consultation with local and regional
transportation agencies. Present solutions intended to address transportation
system needs related to the park.
(13) Assess the potential impacts of proposed
park uses and facilities and resource management guidelines on local and
regional public services, in consultation with local and regional public
service providers. Present solutions intended to address significant
impacts.
(14) Assess the potential
impacts of preliminary proposed park uses and facilities and resource
management guidelines on adjacent land uses, in consultation with local
governments and others. Present solutions intended to address potentially
significant impacts.
(15) Assess
the compatibility of preliminary proposals for the park with the statewide land
use goals, ORS 215.296, and local planning and
zoning. Identify land use actions needed to achieve compatibility with local
comprehensive plans.
(16) Produce
the draft master plan. Decisions about the master plan shall be consistent with
the state park master planning criteria described under OAR
736-018-0020. The master plan
shall include:
(a) A summary of the resource
and recreation assessments;
(b) A
summary of the compiled issues;
(c)
Goals for future park use, development, interpretation, expansion, resource
protection and management, and for potential partnerships.
(d) Park facility development proposals in
concept, including the descriptions provided under section (10) of this
rule.
(e) Natural, cultural and
scenic resource management and interpretive guidelines for the park;
(f) Findings describing the compliance of the
master plan with the state land use goals, ORS
215.296, compatibility with
applicable local comprehensive plans, and other findings as needed for local
comprehensive plan amendments;
(g)
A summary of anticipated land use permitting requirements for master plan
proposals;
(h) A summary of
anticipated state and federal permit requirements for master plan
proposals;
(i) Supportive maps and
drawings; and
(j) References to any
background material on file with the Department.
(17) Provide periodic updates to the
Commission and Director on the development of the master plan and comments
received.
(18) Distribute the draft
master plan for public review and solicit comments in the following forums:
(a) At least one meeting of the steering
committee;
(b) At least one public
meeting held in the vicinity of the park and at least one other public meeting
in a location that encourages broad participation, each followed by a public
comment period of at least 30 days to provide for submittal of written
comments. The draft master plan shall be offered to the public by media
advertisement and mailed to all those on the master plan mailing list who
request a copy; and
(c) Informal
meetings with Department staff and other agencies and interest groups as
needed.
(19) Following
the public comment period for the draft master plan, assess the comments
received and make appropriate changes based on direction from the
Director.
(20) Present the master
plan to the Commission at their public meeting, and ask for their concurrence
and permission to initiate the rule-making process. Include in the presentation
a summary of the public involvement process and comments. The draft master
plan, recommended changes, and notice of presentation to the Commission shall
be mailed to all those on the master plan mailing list who request a
copy.
(21) Make appropriate changes
to the draft master plan based on direction from the Commission and
Director.
(22) Coordinate with
affected local governments in the development, review and adoption of the
master plan as described in OAR
736-018-0028 and OAR 660
Division 34.
(23) Complete the
rule-making process with related hearings and final edits.
Notes
Stat. Auth.: ORS 390.180
Stats. Implemented: ORS 390.180
State regulations are updated quarterly; we currently have two versions available. Below is a comparison between our most recent version and the prior quarterly release. More comparison features will be added as we have more versions to compare.
No prior version found.