Or. Admin. Code § 736-146-0060 - Payment Authorization of Cost Overruns for Goods or Services including Architectural, Engineering and Land Surveying Services and Related Services Contracts
(1)
Payments on contracts that exceed the maximum contract consideration require
approval from OPRD's designated procurement officer and may require approval
from the Department of Justice pursuant to OAR
137-045-0010 et seq. Approval
may be provided if there is compliance with all of the following:
(a) The original contract was duly executed
and, if required, approved by the Attorney General.
(b) The original contract has not expired,
been terminated, or been reinstated under OAR
736-147-0070 as of the date
written approval to increase the contract amount is granted.
(c) The cost overrun is not associated with
any change in the statement of work set out in the original contract.
(d) The cost overrun arose out of
extraordinary circumstances or conditions encountered in the course of contract
performance that were reasonably not anticipated at the time the original
contract or the most recent amendment, if any, was signed. Such circumstances
include but are not limited to cost overruns that:
(A) Address emergencies arising in the course
of the contract that require prompt action to protect the work already
completed.
(B) Comply with official
or judicial commands or directives issued during contract
performance.
(C) Ensure that the
purpose of the contract will be realized;
(e) The cost overrun was incurred in good
faith, results from the good faith performance by the contractor, and is no
greater than the prescribed hourly rate or the reasonable value of the
additional work or performance rendered.
(f) Except for the cost overrun, the contract
and its objective are within the statutory authority of OPRD and OPRD currently
has funds available for payment under the contract.
(g) An officer or employee of OPRD has
presented a written report to OPRD's designated procurement officer within 60
days of the discovery of the overrun that states the reasons for the cost
overrun and demonstrates to the satisfaction of OPRD's designated procurement
officer that the original contract and the circumstances of the overrun satisfy
the conditions stated above.
(h)
OPRD's designated procurement officer approves in writing the payment of the
overrun, or such portion of the overrun amount as OPRD's designated procurement
officer determines may be paid consistent with the conditions of this rule. If
OPRD's designated procurement officer has signed the contract, or has immediate
supervisory responsibility over performance of the contract, that person must
designate an alternate delegate to grant or deny written approval of
payment.
(2) OPRD must
obtain an Attorney General's approval of the contract amendment, if such
approval is required by ORS
291.047, before making any
overrun payment.
Notes
Stat. Auth.: ORS 279A.065(5)(a) & 279A.070
Stats. Implemented: ORS 279A.065(5)(a), 279A.070 & 279A.140
State regulations are updated quarterly; we currently have two versions available. Below is a comparison between our most recent version and the prior quarterly release. More comparison features will be added as we have more versions to compare.
No prior version found.