Or. Admin. Code § 839-025-0020 - Public Works Contracts and Contract Specifications; Required Conditions
(1) For
purposes of this rule:
(a) "Construction
Manager/General Contractor contract" (or "CM/GC contract") means a contract
that typically results in a general contractor/construction manager initially
undertaking various pre-construction tasks that may include, but are not
limited to: design phase development, constructability reviews, value
engineering, scheduling, and cost estimating, and in which a guaranteed maximum
price for completion of construction-type work is typically established by
amendment of the initial contract, after the pre-construction tasks are
complete or substantially complete. "CM/GC" refers to the general
contractor/construction manager under this form of contract. Following the
design phase, the CM/GC may then act as a General Contractor and begin the
subcontracting process. The CM/GC typically coordinates and manages the
construction process, provides contractor expertise, and acts as a member of
the project team.
(b) "Construction
specifications" include the detailed description of physical characteristics of
the improvement, design details, technical descriptions of the method and
manner of doing the work, quantities or qualities of any materials required to
be furnished, descriptions of dimensions, required units of measurement,
composition or manufacturer, and descriptions of any quality, performance, or
acceptance requirements.
(2) Every public works contract must contain
the following:
(a) A condition or clause that,
if the contractor fails, neglects, or refuses to make prompt payment of any
claim for labor or services furnished to the contractor or a subcontractor by
any person, or the assignee of the person, in connection with the public works
contract as such claim becomes due, the proper officer or officers of the
public agency may pay such claim and charge the amount of the payment against
funds due or to become due the contractor by reason of the contract (Reference:
ORS 279C.515);
(b) A condition that no person will be
employed for more than 10 hours in any one day, or 40 hours in any one week
except in cases of necessity, emergency, or where the public policy absolutely
requires it, and in such cases the person so employed must be paid at least
time and one-half the regular rate of pay for all time worked:
(A) For all overtime in excess of eight hours
a day or 40 hours in any one week when the work week is five consecutive days,
Monday through Friday; or
(B) For
all overtime in excess of 10 hours a day or 40 hours in any one week when the
work week if four consecutive days, Monday through Friday; and
(C) For all work performed on Saturday and on
any legal holiday specified in ORS
279C.540 (Reference: ORS
279C.520(1));
(c) A condition that an employer
must give notice to employees who work on a public works contract in writing,
either at the time of hire or before commencement of work on the contract, or
by posting a notice in a location frequented by employees, of the number of
hours per day and days per week that the employees may be required to work
(Reference: ORS 279C.520(2));
and
(d) A condition that the
contractor must promptly, as due, make payment to any person, co-partnership,
association or corporation, furnishing medical, surgical and hospital care or
other needed care and attention, incident to sickness or injury, to employees
of such contractor, of all sums which the contractor agrees to pay for such
services and all moneys and sums which the contractor collected or deducted
from the wages of the contractor's employees pursuant to any law, contract or
agreement for the purpose of providing or paying for such service (Reference:
ORS 279C.530).
(3) Every public works contract that a public
agency awards must contain a condition or clause that requires the contractor
to:
(a) Have a public works bond filed with
the Construction Contractors Board before starting work on the project, unless
the contractor is exempt under ORS
279C.836(4), (7), (8) or
(9).
(b) Require, in every subcontract, that the
subcontractor have a public works bond filed with the Construction Contractors
Board before starting work on the project, unless the subcontractor is exempt
under ORS 279C.836(4), (7), (8) or
(9).
(4) Every subcontract that a contractor or
subcontractor awards in connection with a public works contract between a
contractor and a public agency must require any subcontractor to have a public
works bond filed with the Construction Contractors Board before starting work
on the public works projects, unless the subcontractor is exempt under ORS
279C.836 (4), (7), (8), or
(9).
(5)
(a)
Every public works contract and subcontract must provide that each worker the
contractor, subcontractor or other person who is a party to the contract uses
in performing all or part of the contract, must be paid not less than the
applicable prevailing rate of wage for each trade or occupation as defined by
the Commissioner of the Bureau of Labor and Industries in the applicable
publication entitled Definitions of Covered Occupations for Public Works
Contracts in Oregon.
(b) If a
public works project is subject to both ORS
279C.800 to ORS
279C.870 and to the Davis-Bacon
Act (40 U.S.C.
3141 et seq.), every public works contract
and subcontract must provide that the worker whom the contractor, subcontractor
or other person who is a party to the contract uses in performing all or part
of the contract, must be paid not less than the higher of the applicable state
prevailing rate of wage for each trade or occupation as defined by the
Commissioner of the Bureau of Labor and Industries in the applicable
publication entitled Definitions of Covered Occupations for Public Works
Contracts in Oregon or federal prevailing rate of wage.
(6)
(a) The
specifications for every public works contract must contain a provision that
states the existing state prevailing rate of wage and, if applicable, the
federal prevailing rate of wage required under the Davis-Bacon Act
(40 U.S.C.
3141 et seq.).
(b) Except as provided in subsection (d) of
this section and sections (8) and (9) of this rule, the existing state
prevailing rate of wage and the applicable publication entitled Definitions of
Covered Occupations for Public Works Contracts in Oregon are those in effect at
the time the initial specifications were first advertised for bid
solicitations.
(c) If a public
agency is required under subsection (a) of this section or section (8) of this
rule to include the state and federal prevailing rates of wage in the
specifications for a contract for public works, the public agency shall also
include in the specifications the requirement that the contractor pay the
higher of the applicable state or federal prevailing rate of wage to all
workers on the public works project.
(d) Pursuant to ORS
279C.838(4) and
notwithstanding ORS 279C.830(1), if
the contract is subject to both ORS
279C.800 to
279C.870 and the Davis Bacon Act
(40 U.S.C.
3141 et seq.), the public agency may provide
in the specifications for the contract a single date to be used to establish
the "existing state prevailing rate of wage," the applicable publication
entitled Definitions of Covered Occupations for Public Works Contracts in
Oregon, and the "applicable federal prevailing rate of wage" that is consistent
with the federal requirements under
29 CFR
1.6.
(e) The specifications for a contract for
public works must provide that the contractor and every subcontractor must have
a public works bond filed with the Construction Contractors Board before
starting work on the project, unless the contractor or subcontractor is exempt
under ORS 279C.836(4), (7), (8) or
(9).
(7)
(a) The
provisions described in sections (5) and (6), and sections (8) and (9) if
applicable, must be included in all specifications for each contract awarded on
the project, regardless of the price of any individual contract, so long as the
combined price of all contracts awarded on the project is $50,000 or more
(Reference: ORS 279C.830).
(b) A statement incorporating the applicable
state prevailing wage rate publication and any amendments thereto into the
specifications by reference will satisfy these requirements. Except as provided
in subsection (c), such reference must include the title of the applicable wage
rates publication or determination and the date of the publication or
determination as well as the date of any applicable amendments.
(c) When the prevailing wage rates are
available electronically or are accessible on the Internet, the rates may be
incorporated into the specifications by referring to the electronically
accessible or Internet-accessible rates and by providing adequate information
about how to access the rates. Such reference must include the title of the
applicable wage rates publication or determination and the date of the
publication or determination as well as the date of any applicable amendments.
The reference requirements of this subsection will be satisfied if such
reference includes Uniform Resource Locator (URL) information for a webpage or
webpages showing the title of each applicable wage rates publication or
determination and the date of each publication or determination as well as the
date of any applicable amendments.
(8)
(a)
When a public agency is a party to a CM/GC contract, the CM/GC contract becomes
a public works contract either when the contract first constitutes a binding
and enforceable obligation on the part of the CM/GC to perform or arrange for
the performance of construction, reconstruction, major renovation, demolition,
removal of hazardous waste or painting of an improvement that is a public works
or when the CM/GC contract enters the construction phase, whichever occurs
first.
(b) For example, the CM/GC
will have a binding and enforceable obligation to perform or arrange for the
performance of construction, reconstruction, major renovation, demolition,
removal of hazardous waste or painting of an improvement after the public
agency and CM/GC commit to the guaranteed maximum price.
(c) For purposes of this rule, the CM/GC
contract enters the construction phase when the agency first authorizes the
performance of early construction, reconstruction, major renovation,
demolition, removal of hazardous waste or painting work directly related to the
improvement project.
(d) The
publication entitled Definitions of Covered Occupations for Public Works
Contracts in Oregon and the prevailing wage rate in effect at the time the
CM/GC contract becomes a public works contract shall apply and the applicable
prevailing wage rates must be included with the construction specifications for
the CM/GC contract.
(9)
A public works project described in ORS
279C.800(6)(a)(B), (C), (D), (E) or
(F) that is not a CM/GC contract subject to
section (8) of this rule, and for which no public agency awards a contract to a
contractor for the project, is subject to the publication entitled Definitions
of Covered Occupations for Public Works Contracts in Oregon and the existing
state prevailing rate of wage or, if applicable, the federal prevailing rate of
wage required under the Davis-Bacon Act that are in effect at the time a public
agency enters into an agreement with a private entity for the project. (Note:
The effective date of the applicable federal prevailing rate of wage may be
different under federal law.) After that time, the specifications for any
contract for the public works shall include the applicable prevailing rate of
wage.
(10) If a project is a public
works of the type described in ORS
279C.800(6)(a)(B), (C), (D), (E) or
(F) and no public agency awards a contract to
a contractor for the project, a public agency will be deemed to have complied
with the provisions of ORS
279C.830 if the public agency
requires compliance with the provisions of section (7) of this rule in any
agreement entered into by the public agency committing to provide funds for the
project, to occupy or use the completed project, authorizing the construction
or installation of a solar radiation device, or authorizing demolition or
hazardous waste removal.
(11)
Public agencies may obtain, without cost, a copy of the existing state
prevailing rate of wages for use in preparing the contract specifications by
contacting the Prevailing Wage Rate Unit or any office of the bureau.
Notes
Statutory/Other Authority: ORS 651.060 & ORS 279C.808
Statutes/Other Implemented: ORS 279C.800 - 279C.870
State regulations are updated quarterly; we currently have two versions available. Below is a comparison between our most recent version and the prior quarterly release. More comparison features will be added as we have more versions to compare.
No prior version found.