Or. Admin. Code § 860-023-0131 - Customer Inquiries about Electric Reliability
(1) A customer may request a report from an
electric company about the service reliability provided to the customer's own
meter. Within 20 business days, the electric company must supply the report to
the customer at no cost. However, if a customer requests an additional
reliability report for the same meter within one year of the date of the first
request, the electric company may charge the customer the actual cost for the
report.
(2) The report must
include:
(a) The name of the
customer;
(b) The date of the
request;
(c) The address where the
meter is installed;
(d) The meter
number involved;
(e) The circuit
involved; and
(f) A chronological
listing, covering at least the 36 months preceding the date of the request, of
all interruption data as required by OAR
860-023-0101 affecting the
customer's meter.
(3)
This rule is effective beginning January 1, 2012.