Or. Admin. Code § 860-025-0035 - CPCN Review Criteria
(1) The
Commission may approve a petition filed under OAR
860-025-0030 by determining the
necessity, safety, practicability and justification in the public interest of
the proposed transmission line upon consideration of the following:
(a) Whether the transmission line will meet a
demonstrated need for transmission of additional capacity or improved system
reliability that enables the petitioner to provide or continue to provide
adequate and reliable electricity service;
(b) Whether the petitioner has demonstrated
that it will ensure the transmission line is constructed, operated, and
maintained in a manner that protects the public from danger and conforms with
applicable Commission rules, and other applicable safety standards and best
industry practices;
(c) Whether the
transmission line using petitioner's proposed route is practicable and
feasible, whether it will be effectively and efficiently constructed in a
commercially reasonable manner;
(d)
Whether petitioner has justified construction of the proposed transmission line
as in the public interest, as compared with feasible alternatives for meeting
the identified need, considering the public benefits and costs of the project,
as they relate to the interests in land proposed to be condemned, petitioner's
existing facilities and equipment, petitioner's Oregon customers, and other
considerations that may be relevant to the public interest. Other such
considerations include, but are not limited to, the benefits and costs to other
Oregon utilities, their customers, and all Oregonians, the value of connections
to regional and inter-regional electricity grids and to a petitioner's
non-Oregon service territories, and all Oregonians;
(e) The Commission may also consider other
factors it deems relevant to the statutory criteria.
(2) In evaluating a petition under this rule,
the Commission will give due consideration to related regulatory reviews and
permitting approvals as pertinent to the proposed transmission line, if the
transmission line has already been acknowledged or approved by regulatory or
permitting authorities.
(3) In the
event a CPCN is granted, the certificate shall expire 15 years from date of
issuance, except that a certificate shall expire 10 years from the date of
issuance if construction has not commenced during those 10 years. Upon written
request of a petitioner, the Commission may grant an extension on the term of a
certificate for good cause shown. A request must be served on the service list
for the associated CPCN docket, and if applicable, the docket for the
petitioner's last acknowledged integrated resource plan.
Notes
Statutory/Other Authority: ORS 183, ORS 756 & ORS 758
Statutes/Other Implemented: ORS 758.015
State regulations are updated quarterly; we currently have two versions available. Below is a comparison between our most recent version and the prior quarterly release. More comparison features will be added as we have more versions to compare.
No prior version found.