Or. Admin. Code § 860-028-0100 - Application Process for New or Modified Attachments
(1) As used in this rule, "applicant" does
not include a government entity.
(2) An applicant requesting a new or modified
attachment must submit an application providing the following information in
writing or electronically to the owner:
(a)
Information for contacting the applicant.
(b) The pole owner may require the applicant
to provide the following technical information:
(A) Location of identifying pole or conduit
for which the attachment is requested;
(B) The amount of space requested;
(C) The number and type of attachment for
each pole or conduit;
(D) Physical
characteristics of attachments;
(E)
Attachment location on pole;
(F)
Description of installation;
(G)
Proposed route; and
(H) Proposed
schedule for construction.
(3) The owner must provide written or
electronic notice to the applicant within 15 days of the application receipt
date confirming receipt and listing any deficiencies with the application,
including missing information. If required information is missing, the owner
may suspend processing the application until the missing information is
provided.
(4) Upon receipt of a
completed application, an owner must reply in writing or electronically to the
applicant as quickly as possible and no later than 45 days from the date the
completed application is received. The owner's reply must state whether the
application is approved, approved with modifications or conditions, or denied.
(a) An approval will be valid for 180
calendar days unless extended by the owner.
(b) The owner may require the applicant to
provide notice of completion within 45 calendar days of completion of
construction.
(c) If the owner
approves an application that requires make ready work, the owner must provide a
detailed list of the make ready work needed to accommodate the applicant's
facilities, an estimate for the time required for the make ready work, and the
cost for such make ready work.
(d)
If the owner denies the application, the owner must state in detail the reasons
for its denial.
(e) If the owner
does not provide the applicant with notice that the application is approved,
denied, or conditioned within 45 days from its receipt, the applicant may begin
installation. Applicant must provide notice prior to beginning installation.
Commencement of installation by the occupant will not be construed as
completion of the permitting process or as final permit approval. Unpermitted
attachments made under this section are not subject to sanction under OAR
860-028-0140.
(5) If the owner approves an
application that requires make ready work, the owner will perform such work at
the applicant's expense. This work must be completed in a timely manner and at
a reasonable cost. Where this work requires more than 45 days to complete, the
parties must negotiate a mutually satisfactory longer period to complete the
make ready work.
(6) If an owner
cannot meet the time frame for attachment established by this rule,
preconstruction activity and make ready work may be performed by a mutually
acceptable third party.
(7) If an
application involves more than the threshold number of poles, the parties must
negotiate a mutually satisfactory longer time frame to complete the approval
process.
Notes
Stat. Auth.: ORS 183, 756, 757 & 759
Stats. Implemented: ORS 756.040, 757.035, 757.270 - 290, 759.045 & 759.650 - 675
State regulations are updated quarterly; we currently have two versions available. Below is a comparison between our most recent version and the prior quarterly release. More comparison features will be added as we have more versions to compare.
No prior version found.