Or. Admin. Code § 860-029-0130 - Nonstandard Power Purchase Agreements
(1) Each public utility must offer
nonstandard avoided cost rates and nonstandard power purchase agreements to all
qualifying facilities directly or indirectly interconnected with the public
utility.
(2) Qualifying facilities
have the unilateral right to select a purchase term of up to 20 years for a
power purchase agreement. Qualifying facilities electing to sell firm output at
fixed prices have the unilateral right to a fixed-price term of up to 15
years.
(3) A qualifying facility
may specify a scheduled commercial on-line date consistent with the following:
(a) Anytime within three years from the date
of agreement execution;
(b) Anytime
later than three years after the date of agreement execution if the qualifying
facility establishes to the utility that a later scheduled commercial on-line
date is reasonable and necessary and the utility agrees.
(4) The qualifying facility will be
determined to be providing firm energy or capacity if the contract requires
delivery of a specified amount of energy or capacity over a specified term and
includes sanctions for noncompliance under a legally enforceable obligation.
For a qualifying facility providing firm energy or capacity:
(a) The utility and the qualifying facility
should negotiate the time periods when the qualifying facility may schedule
outages and the advance notification requirement for such outages, using
provisions in the utility's partial requirements tariffs as guidance.
(b) The qualifying facility should be
required to make best efforts to meet its capacity obligations during the
utility system emergencies.
(c) The
utility and the qualifying facility should negotiate security, default, damage
and termination provisions that keep the utility and its ratepayers whole in
the event the qualifying facility fails to meet its obligations under the
contract.
(d) Delay of commercial
operation should not be a cause of termination if the utility determines at the
time of contract execution that it will be resource sufficient as of the
qualifying facility scheduled commercial operation date specified in the power
purchase agreement. The utility may impose damages.
(e) Lack of notice force testing to prove
commercial operation should not be the cause of termination.
(5) An "as-available" obligation
for delivery of energy, including deliveries in excess of nameplate rating or
the amount committed in the power purchase agreement should be treated as a
non-firm commitment. Non-firm commitment should not be subject to minimum
delivery requirements, default damages for construction delay or
under-delivery, default damages for the qualifying facility choosing to
terminate the power purchase agreement early, or default security for these
purposes.
(6) For qualifying
facilities unable to establish creditworthiness, the utility must at a minimum
allow the qualifying facility to choose either a letter of credit or cash
escrow for providing default security. When determining security requirements,
the utility should take into account the risk associated with the qualifying
facility based on such factors such as its size and type of supply commitments.
Default security methodologies specified in the utility's standard power
purchase agreements are a useful starting point for negotiations for
nonstandard power purchase agreements.
(7) Qualifying facilities may either contract
with the purchasing utility for a "surplus sale" or for a "simultaneous
purchase and sale" provided, however, that the qualifying facility's selection
of either contractual arrangement is not inconsistent with any retail tariff
provision of the purchasing utility then in effect or any agreement between the
qualifying facility and the purchasing utility.
(a) Contracts for surplus sale and for
simultaneous purchase and sale will be available to qualifying facilities
regardless of whether they qualify for standard power purchase agreements and
rates or non-standard power purchase agreements and rates. However, the
"simultaneous purchase and sale" is not available to qualifying facilities not
directly connected to the purchasing utility's electrical system.
(b) The negotiation parameters and guidelines
should be the same for both surplus sale and simultaneous purchase and sale
contracts.
(c) The avoided cost
calculations by utilities do not require adjustment solely as a result of the
selection of either surplus sale or simultaneous purchase and sale
arrangements.
Notes
Statutory/Other Authority: ORS 183, 756, 757, 758
Statutes/Other Implemented: ORS 756.040, 758.505-758.555
State regulations are updated quarterly; we currently have two versions available. Below is a comparison between our most recent version and the prior quarterly release. More comparison features will be added as we have more versions to compare.
No prior version found.