Or. Admin. Code § 860-039-0030 - Tier 1 Net Metering Interconnection Review
(1) A net metering facility meeting the
following criteria is eligible for Tier 1 interconnection review:
(a) The facility is inverter-based;
and
(b) The facility has a
generation capacity of 50 kilowatts or less and an export capacity of 25
kilowatts or less.
(2)
The public utility must approve a complete application for interconnection
under the Tier 1 net metering interconnection review procedure if the net
metering facility meets the eligibility requirements in section (1) of this
rule and the facility meets the Tier 1 interconnection screening criteria set
forth in OAR 860-082-0045(2)(a)-(f):
(3) Within 10 business days after the public
utility notifies a Tier 1 applicant that the application is complete, the
public utility must notify the applicant whether the facility meets the Tier 1
screening criteria.
(4) If a public
utility does not notify a Tier 1 applicant in writing or by electronic mail
whether the interconnection application passes the Tier 1 screening criteria
within 20 business days after the receipt of a complete application, the
interconnection application will be deemed approved. Interconnections approved
under this section remain subject to sections (7) and (8) below.
(5) Approval despite screen failure.
(a) Despite the failure of one or more
screening criteria, the public utility, at its sole option, may approve the
interconnection provided such approval is consistent with safety and
reliability.
(b) If the public
utility determines that the customer-generator can be interconnected safely if
minor modifications to the transmission or distribution system were made (for
example, changing meters, fuses, or relay settings), then the public utility
must offer the applicant a good-faith, non-binding estimate of the costs of
such proposed minor modifications. Modifications are not considered minor under
this subsection if the total cost of the modifications exceeds $10,000. If the
applicant authorizes the public utility to proceed with the minor modifications
and agrees to pay the entire cost of the modifications, then the public utility
must approve the application.
(6) Process after screen failure. If the
public utility cannot determine that the customer-generator may nevertheless be
interconnected consistent with safety, reliability, and power quality
standards, at the time the public utility notifies the applicant of the Tier 1
review results the public utility shall provide the applicant with:
(a) The screen results, including specific
information on the reason(s) for failure in writing using a standard format
approved by the Commission; and
(b)
An executable Supplemental Review Agreement.
(c) In addition, the public utility shall
allow the applicant to select one of the following, at the applicant's option:
(A) Request an applicant options
meeting;
(B) Undergo supplemental
review in accordance with OAR
860-082-0063; or
(C) Continue evaluating the application under
Tier 4.
(d) The
applicant must notify the public utility of its selection under subsection (c)
within 10 business days, or the application will be deemed withdrawn.
(7) Applicant options meeting. If
the applicant requests an applicant options meeting, the public utility shall
offer to convene a meeting at a mutually agreeable time within 15 business days
of the applicant's request. At the applicant options meeting, the public
utility shall provide the applicant the opportunity to review the screen
analysis and related results, to designate a different RPA, to review possible
customers-generator modifications, and to discuss what further steps are needed
to permit the net metering facility to connect safely and reliably.
(8) With three business days after sending
the notice to an applicant that the proposed interconnection application meets
the Tier 1 interconnection requirements, a public utility must notify the
applicant whether:
(a) An inspection of the
net metering facility for compliance with the net metering rules is required
prior to the operation of the facility; and
(b) An interconnection agreement is required
for the net metering facilities. If required, the public utility must also
execute and send to the applicant a Tier 1 interconnection agreement, unless
the applicant has already submitted such an agreement with its application for
interconnection.
(9) On
receipt of any required executed interconnection agreement from the applicant
and satisfactory completion of any required inspection, the public utility will
approve the interconnection, conditioned on compliance with all applicable
building codes.
(10) A
customer-generator will notify the public utility of the anticipated start date
for operation of the net metering facility at least five business days prior to
starting operation, either through the submittal of the interconnection
agreement or in a separate notice. If the public utility requires an inspection
of the net metering facility, the applicant will not begin operating the
facility until satisfactory completion of the inspection.
Notes
Statutory/Other Authority: ORS 183, ORS 756 & ORS 757
Statutes/Other Implemented: ORS 756.040 & ORS 757.300
State regulations are updated quarterly; we currently have two versions available. Below is a comparison between our most recent version and the prior quarterly release. More comparison features will be added as we have more versions to compare.
No prior version found.