Or. Admin. Code § 860-039-0040 - Tier 4 Net Metering Interconnection Review
(1) The public utility must apply the Tier 4
review procedure for an application to interconnect a net metering facility
that meets the following criteria:
(a) The
facility has a capacity of two megawatts or less; and
(b) The facility does not qualify for or
failed to receive approval in Tier 1 or Tier 2 interconnection review
procedures.
(2)
Following receipt of a Tier 4 application and within three business days of a
request from the applicant, the public utility must provide pertinent
information to the applicant, such as the available fault current at the
proposed interconnection location, the existing peak loading on the lines in
the general vicinity of the net metering facility, and the configuration of the
distribution lines at the proposed point of common coupling.
(3) Within seven business days after
receiving a complete application for Tier 4 interconnection review, the public
utility must provide an impact study agreement to the applicant, which will
include a non-binding, good faith cost estimate for an impact study to be
performed by the public utility. The impact study will be conducted in
accordance with good utility practice and must:
(a) Detail the impacts to the electric
distribution system that would result if the net metering facility were
interconnected without modifications to either the net metering facility or to
the electric distribution system;
(b) Identify any modifications to the public
utility's electric distribution system that would be necessary to accommodate
the proposed interconnection;
(c)
Focus on power flows and utility protective devices, including control
requirements; and
(d) Include the
following elements, as applicable:
(A) A load
flow study;
(B) A short-circuit
study;
(C) A circuit protection and
coordination study;
(D) The impact
on the operation of the electric distribution system;
(E) A stability study, along with the
conditions that would justify including this element in the impact
study;
(F) A voltage collapse
study, along with the conditions that would justify including this element in
the impact study; and
(G)
Additional elements, if approved in writing by Commission staff prior to the
impact study.
(4) After the applicant executes the impact
study agreement and pays the public utility the amount of the good faith
estimate, the public utility will complete the impact study and will notify the
applicant within 30 calendar days of one of the following results:
(a) Only minor modifications to the public
utility's electric distribution system are necessary to accommodate
interconnection. In such a case, the public utility will send the applicant an
interconnection agreement that details the scope of the necessary modifications
and a non-binding, good faith estimate of their cost; or
(b) Substantial modifications to the public
utility's electric distribution system are necessary to accommodate the
proposed interconnection. In such a case, the public utility must provide a
non-binding, good faith estimate of the cost of the modifications, which must
be accurate to within plus or minus 25 percent. In addition, the public utility
must offer to conduct, at the applicant's expense, an interconnection
facilities study that must identify the types and cost of equipment needed to
safely interconnect the applicant's net metering facility.
(5) If the proposed interconnection may
affect electric transmission or delivery systems other than those controlled by
the public utility, operators of those other systems may require additional
studies to determine the potential impact of the interconnection on those
systems. If such additional studies are required, the public utility will
coordinate the studies but will not be responsible for their timing. The
applicant will be responsible for the costs of any such additional studies
required by another affected system. Such studies will be conducted only after
the applicant has provided written authorization.
(6) If an applicant requests a facilities
study under subsection (4)(b), the public utility must provide an
interconnection facilities study agreement. The interconnection facilities
study agreement must describe the work to be undertaken in the interconnection
facilities study and must include a non-binding, good faith estimate of the
cost to the applicant for completion of the study. Upon the execution by the
applicant of the interconnection facilities study agreement, the public utility
will conduct an interconnection facilities study to identify the facilities
necessary to safely interconnect the net metering facility with the public
utility's electric distribution system, and to propose a non-binding, good
faith estimate of the cost of those facilities and the time required to build
and install those facilities.
(7)
Upon completion of an interconnection facilities study, the public utility must
provide the applicant with the results of the study and an executable
interconnection agreement. The agreement must list the conditions and
facilities necessary for the net metering facility to safely interconnect with
the public utility's electric distribution system, and must include a
non-binding, good faith estimate of the cost of those facilities and the
estimated time required to build and install those facilities.
(8) If the applicant wishes to interconnect,
it must execute the interconnection agreement and return it to the public
utility at least 10 business days prior to starting operation of the net
metering facility (unless the public utility does not so require), pay a
deposit of not more than 50 percent of the estimated cost of the facilities
identified in the interconnection facilities study, complete installation of
the net metering facility, and agree to pay the public utility the actual
installed cost of the facilities needed to interconnect as identified in the
interconnection facilities study.
(9) Within 15 business days after notice from
the applicant that the net metering facility has been installed, the public
utility will inspect the net metering facility and will arrange to witness any
commissioning tests required under IEEE standards. The public utility and the
applicant will select a date by mutual agreement for the public utility to
witness commissioning tests.
(10)
If the net metering facility satisfactorily passes required commissioning
tests, if any, the public utility must notify the applicant in writing, within
three business days after the tests, of one of the following:
(a) The interconnection is approved, and the
net metering facility may begin operation; or
(b) The interconnection facilities study
identified necessary construction that has not been completed, the date upon
which the construction will be completed and the date when the net metering
facility may begin operation.
(11) If the commissioning tests are not
satisfactory, the applicant will repair or replace the unsatisfactory equipment
and reschedule a commissioning test.
Notes
Statutory/Other Authority: ORS 183, ORS 756 & ORS 757
Statutes/Other Implemented: ORS 756.040 & ORS 757.300
State regulations are updated quarterly; we currently have two versions available. Below is a comparison between our most recent version and the prior quarterly release. More comparison features will be added as we have more versions to compare.
No prior version found.