Or. Admin. Code § 860-088-0050 - Project Certification
(1) The
Project Manager of a pre-certified project must submit an application for
project certification to the Program Administrator.
(2) The Commission will certify a project
that demonstrates:
(a) Ownership of, or
subscription to, at least 50 percent of the project nameplate capacity;
(b) Ownership or subscription by
at least five different participants;
(c) Compliance with applicable low-income
capacity requirements;
(d)
Commission approval of modification to pre-certified project as required in OAR
860 088-0040(6), if applicable; and
(e) Satisfaction of any other condition
identified by the Commission at the time of pre certification.
(3) The Program Administrator
reviews applications for certification in the order received for compliance
with applicable requirements and presents applications to the Commission for
certification. The Program Administrator must notify the Project Manager of any
deficiencies and allow reasonable time for remedy.
Notes
Stat. Auth.: OL 2016, ch. 28, sec. 22
Stats. Implemented: OL 2016, ch. 28, sec. 22