(1) To participate in the Community Solar
Program, a project must:
(a) Be located
within the Oregon service territory of an electric company; and
(b) Have a nameplate capacity of three
megawatts or less.
(2)
"Co-location" means two or more projects that exhibit characteristics of a
single development, such as common ownership structure, an umbrella sale
arrangement, revenue-sharing arrangements, or common debt or equity financing.
Projects are not considered co located solely because the same person provides
tax equity financing for the projects. Co location of projects is not permitted
within a five-mile radius unless:
(a) The
aggregate nameplate capacity of the co-located projects is three megawatts or
less; or
(b) The co-located
projects are all sited within a single municipality or urban area as defined in
the Program Implementation Manual.
(3) Multiple solar photovoltaic energy
systems that are aggregated into one project must all be located within a
single electric company's service territory.
Notes
Stat. Auth.: OL 2016, ch. 28, sec. 22
Stats. Implemented: OL 2016, ch. 28, sec. 22
State regulations are updated quarterly; we currently have two versions available. Below is a comparison between our most recent version and the prior quarterly release. More comparison features will be added as we have more versions to compare.
No prior version found.