Or. Admin. Code § 860-088-0140 - Sale and Purchase of Unsold and Unsubscribed Generation
(1) Upon project certification, the project's
remaining unsold and unsubscribed generation is eligible for sale subject to
the following requirements:
(a) Upon request,
an electric company must enter into a 20-year power purchase agreement with a
pre-certified project to purchase the project's unsold and unsubscribed
generation on an "as available" basis subject to the requirements of the Public
Utility Regulatory Policy Act (PURPA) and ORS
758.505, et. seq.;
(b) If the electric company is the Project
Manager, the electric company may seek Commission approval to recover from all
ratepayers the "as available" rate for the project's unsold and unsubscribed
generation; and
(c) Renewable
energy certificates associated with generation sold under section (1)(a) of
this rule at the "as available" rate will not transfer to the electric company
unless otherwise agreed by the Project Manager and electric company.
(2) The value of any project
generation that is not sold to or subscribed by participants, sold to an
electric company under a power purchase agreement, or sold on another basis
must be donated to the electric company whose service territory encompasses the
project at the "as available" rate and used by the electric company to assist
low-income residential customers' participation in the Community Solar
Program.
Notes
Stat. Auth.: OL 2016, ch. 28, sec. 22
Stats. Implemented: OL 2016, ch. 28, sec. 22