Or. Admin. Code § 860-089-0500 - Final Short List Acknowledgement and Result Publication
(1) For the purposes of this section,
"acknowledgment" is a finding by the Commission that an electric company's
final shortlist of bid responses appears reasonable at the time of
acknowledgment and was determined in a manner consistent with the rules in this
division.
(2) An electric company
must request that the Commission acknowledge the electric company's final
shortlist of bids before it may begin negotiations. Acknowledgment of a
shortlist has the same legal force and effect as a Commission-acknowledged IRP
in any future cost recovery proceeding.
(3) A request for acknowledgement must
include, at a minimum, the IE's closing report, the electric company's final
shortlist of responsive bids, all sensitivity analyses performed, and a
discussion of the consistency between the final shortlist and the electric
company's last-acknowledged IRP Action Plan or acknowledged IRP
Update.
(4) The Commission will
generally issue a decision on the request for acknowledgment within 60 days of
receipt of the electric company's filing.
(5) The electric company must make a publicly
available filing in the RFP docket providing the average bid score and the
average price of a resource on its final shortlist.
(6) Following execution of all contracts
resulting from an RFP or cancellation of the RFP, the electric company must
provide information, on request, to a bidder about the bidder's bid
score.
Notes
Statutory/Other Authority: ORS Ch. 183, 756, 758, 2016 OL Ch. 28
Statutes/Other Implemented: ORS 756.040, 758.060, 2016 OL Ch. 28, Sect. 6