Or. Admin. Code § 918-305-0520 - Time Limit for Plan Review
(1) Plan reviews shall be approved or denied
within ten working days from receipt of the complete electrified fixed guideway
railway system plans by the jurisdiction requiring plan review. A reviewed set
of plans shall be returned to the plan applicant:
(a) If a plan is rejected, the deficiencies
must be set out in writing. Upon resubmission of the necessary items, the
ten-day requirement starts again;
(b) If, because of the complexity or size of
the installation, additional time beyond the ten working days is required to
complete the review, the jurisdiction shall notify the person taking out the
electrical permit of the reasons for the delay and the date the review will be
completed.
(2) Nothing
in this rule shall prohibit a jurisdiction from issuing a complete or partial
permit before the entire plans and specifications are submitted or approved,
provided adequate information is provided showing compliance with pertinent
portions of the code. The permittee proceeds at risk, without assurance that
the permit for the entire installation will be granted, or that corrections
will not be required including those portions permitted.