Or. Admin. Code § 918-309-0040 - Permit for the Installation, Alteration, or Relocation of an Electrical Service or Feeder
Permanent service or feeder.
(1) Each service or feeder of 200 amps or
less, $79.
(2) Each service or
feeder in excess of 200 amps but not more than 400 amps, $94.
(3) Each service or feeder in excess of 400
amps but not more than 600 amps, $156.
(4) Each service or feeder in excess of 600
amps but not more than 1,000 amps, $204.
(5) Each service or feeder over 1,000 amps or
volts, $469.
(6) General Procedure
for a Separate Service. If a structure has a separate service, the fee is based
on the service size (amps), plus feeders, if any, plus the number of branch
circuits.
(7) Fees in this rule are
in addition to any other fees required under ORS
479.510 to
479.855.
(8) Where the service constitutes a load
center, the permit fee must be calculated the same as any service panel. The
charges must be for the size of the service and the branch circuits or feeders
to the load center.
(9) Reconnect
Only. This rule applies to reconnection where the service was disconnected for
repair or by the serving utility company and no change in service capacity or
location is made. This allows the replacement of a meter base, a service mast,
a service panel, a subpanel, the feeder to one of the items listed or the
repair or replacement of damaged service mast and meter on the exterior of a
building. The $63 fee covers one inspection for this item.
(a) If a major violation of the service
exists, a new service and new permit fee is required;
(b) It may also be used for house moves. If a
major violation of the code or a dangerous condition exists in a house move,
repair or replacement and a permit are required.
(10) Fees charged under this rule may not be
charged both for amps and volts.
(11) In commercial and industrial buildings,
separately metered premises that are divided from each other by walls are
classified as a separate building for the purpose of computing permit fees. A
different permit is required for each separate building:
(a) Master Service. For buildings with a
master service, such as an office building, compute fees by the service (amps),
the feeders (amps) and branch circuits. If there is more than one service, each
service is charged separately along with its related feeders and branch
circuits;
(b) Single Occupant. In
single occupant buildings, the fee is based on the service (amps), the number
of feeders (by amps) and branch circuits;
(c) Tenants. Where tenants are involved, the
shell receives a permit for any service, feeders and branch circuits that
involve only the shell. Each tenant space requires a separate permit. Each
tenant space is charged for service (amps), the number of feeders by amps and
branch circuits.