Or. Admin. Code § 918-400-0640 - Provisional Permits for New Installations

With the exception of private residence installations, a provisional permit may be granted to correct violations of the Oregon Elevator Specialty Code for a new or altered elevator installation, subject to the following:

(1) A written request for the provisional permit is made to the division by the permit holder or the general contractor prior to the commencement of any elevator inspections. If granted, the provisional permit shall not exceed 90 days.
(2) The elevator contractor or general contractor shall make all required corrections and otherwise complete the construction of the installation within the time allotted by the provisional permit. Failure to do so shall result in the elevator being removed from service until such corrections are complete. Mitigating circumstances shall be considered for extending a provisional operating permit as determined by the division.
(3) Provisional permits shall be billed according to OAR 918-400-0800 portal-to-portal.

Notes

Or. Admin. Code § 918-400-0640
BCD 18-1995, f. & cert. ef. 12-15-95; BCD 13-1999, f. & cert. ef. 10-1-99, Renumbered from 918-400-0460

Publications: Publications referenced are available from the agency.

Stat. Auth.: ORS 460.085