Or. Admin. Code § 918-460-0070 - Phased Project and Deferred Submittal Fees
When requested to review and approve plans for phased construction or deferred plan submittals under the Oregon Structural Specialty Code, the following fees in addition to the applicable plan review and permit fees shall apply.
(1) Phased Projects. There shall be an
application fee of $100 for each separate phase of the project. In addition,
the plan review fee shall be increased in an amount equal to 10 percent of the
building permit fee calculated according to OAR
918-460-0050 using the value of
the particular phase of the project, not to exceed an additional $1,500 for
each phase.
(2) Deferred
Submittals. The fee for processing and reviewing deferred plan submittals shall
be an amount equal to 65 percent of the building permit fee calculated
according to OAR 918-460-0050 using the value of
the particular deferred portion or portions of the project. This fee is in
addition to the project plan review fee based on total project value.
Notes
Publications: Publications referenced are available from the agency.
Stat. Auth.: ORS 455.020
Stats. Implemented: ORS 455.020
State regulations are updated quarterly; we currently have two versions available. Below is a comparison between our most recent version and the prior quarterly release. More comparison features will be added as we have more versions to compare.
No prior version found.